Excavation/Setback/Form/Re-Bar
|
11/18/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
11/18/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
11/18/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
11/18/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/15/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
12/15/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
12/16/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
12/16/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
12/19/2022
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
12/19/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
12/20/2022
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
2/7/2023
|
Approved
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
2/7/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
2/8/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
2/9/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
2/22/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
3/2/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
3/2/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
3/2/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
3/24/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
3/24/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
3/24/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
3/28/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
3/29/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/7/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
5/3/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
5/4/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/4/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
5/4/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
5/17/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
5/26/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/26/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
5/26/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
5/26/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
6/5/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Piling/Pier/Caisson
|
6/14/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
6/15/2023
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
6/16/2023
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
7/6/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/7/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
PLUMBING-Rough
|
7/13/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Drilled-In Anchors
|
7/19/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/19/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
7/19/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/24/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/16/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
8/18/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
8/18/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
8/28/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/12/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/19/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Wood Construction
|
10/23/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/8/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
1/8/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Insulation
|
1/8/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
1/8/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
1/8/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
1/8/2024
|
Partial Inspection
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/9/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
1/9/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
1/10/2024
|
Corrections Issued
|
BRENDAN LOONEY
|
|
PLUMBING-Rough
|
1/22/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Shower Pan
|
1/22/2024
|
Approved
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Rough
|
1/25/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
1/25/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
1/29/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
2/2/2024
|
Approved
|
CARLOS MATAMOROS
|
|
BUILDING-Rough-Frame
|
2/8/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Green Building Rough
|
2/8/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Verify Sprinkler Sign Off
|
2/8/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Wood Frame
|
2/8/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Insulation
|
2/21/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
2/21/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
2/27/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
2/27/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
3/20/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
3/20/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
11/7/2024
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
PLUMBING-Final
|
11/8/2024
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Final
|
11/12/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
HVAC-Final
|
11/12/2024
|
Approved
|
SEAN HAUPT
|
|
Final
|
11/13/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
11/13/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Gas Test
|
11/13/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
11/13/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
11/13/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
11/13/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
11/13/2024
|
SGSOV Approved
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
11/13/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
11/13/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
11/14/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
12/4/2024
|
OK to Issue CofO
|
CHRISTOPHER WILSON
|