10901 W SAVONA ROAD 90077

Certificate Information: 10901 W SAVONA ROAD 90077

Application / Permit
21010-10000-06926
Plan Check / Job No.
B21LA24406
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story single family dwelling with roof deck and attached 6-car garage.
Permit Issued
Issued on 10/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 TU HUA
Corrections Issued 1/28/2022 TU HUA
Quality Review Completed 2/7/2022 SAI KHUM
Building Plans Picked Up 2/9/2022 APPLICANT
Applicant returned to address corrections 7/22/2022 TU HUA
Applicant returned to address corrections 7/29/2022 TU HUA
Applicant returned to address corrections 8/17/2022 TU HUA
Applicant returned to address corrections 8/31/2022 TU HUA
Applicant returned to address corrections 9/7/2022 TU HUA
Applicant returned to address corrections 9/14/2022 TU HUA
Plan Check Approved 10/7/2022 TU HUA
Issued 10/7/2022 APPLICANT
CofO in Progress 12/5/2024 CHRISTOPHER WILSON
Permit Finaled 12/9/2024 RICHARD STEINBACH
CofO Issued 12/9/2024 RICHARD STEINBACH
Permit Finaled 12/9/2024 RICHARD STEINBACH

Permit Application Clearance Information

CPC Cleared 2/3/2022 MIGUEL GAMBOA
ZI Cleared 2/3/2022 MIGUEL GAMBOA
Address approval Cleared 2/4/2022 DINAH GARIN
BHO/Hillside ordinance Cleared 2/4/2022 DINAH GARIN
BHO/Hillside ordinance Cleared 2/4/2022 DINAH GARIN
BHO/Hillside ordinance Cleared 2/4/2022 DINAH GARIN
BHO/Hillside ordinance Cleared 2/4/2022 DINAH GARIN
BHO/Hillside ordinance Cleared 2/4/2022 DINAH GARIN
Permit Cleared 2/4/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/7/2022 DINAH GARIN
Sewer availability Cleared 2/7/2022 DINAH GARIN
Hydrant and Access approval Cleared 3/19/2022 DWIGHT SANKEY
Trees in Parkway Cleared 6/24/2022 ADALBERTO VERA
Disturb/Remove Protected Trees Cleared 6/29/2022 ADALBERTO VERA
Low Impact Development Cleared 8/4/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 8/6/2022 STEVEN JIN
GPI Written Notices Cleared 9/7/2022 TU HUA
Grading Pre-Inspection Cleared 9/7/2022 TU HUA

Contact Information

Architect Santiago-Dieppa,, Rafael Angel; Lic. No.: C10361 17116 RAYMER STREET      NORTHRIDGE, CA 91325
Contractor Romm Builders Inc; Lic. No.: 779702-B 5746 RHODES AVE      VALLEY VILLAGE, CA 91607

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/18/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/18/2022 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 11/18/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 11/18/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/15/2022 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 12/15/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 12/16/2022 Not Ready for Inspection CHRISTOPHER WILSON
Piling/Pier/Caisson 12/16/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 12/19/2022 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 12/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 12/20/2022 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 2/7/2023 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 2/7/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/8/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 2/9/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 2/22/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 3/2/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 3/2/2023 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 3/2/2023 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/24/2023 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 3/24/2023 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 3/24/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/28/2023 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/29/2023 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/7/2023 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/3/2023 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/4/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/4/2023 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 5/4/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/17/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/26/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/26/2023 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/26/2023 Not Ready for Inspection CHRISTOPHER WILSON
Piling/Pier/Caisson 5/26/2023 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/5/2023 Conditional Approval MICHAEL PELHAM
Piling/Pier/Caisson 6/14/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/15/2023 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/16/2023 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/6/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/7/2023 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 7/13/2023 Partial Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 7/19/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/19/2023 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/19/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/24/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/16/2023 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 8/18/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/18/2023 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 8/28/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/19/2023 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 10/23/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 1/8/2024 Corrections Issued CHRISTOPHER WILSON
Insulation 1/8/2024 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 1/8/2024 Not Ready for Inspection CHRISTOPHER WILSON
Shower Pan 1/8/2024 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 1/8/2024 Partial Inspection MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Approved CHRISTOPHER WILSON
Pre-Inspection 1/9/2024 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 1/10/2024 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 1/22/2024 Partial Approval STEPHANIE SWANSON
Shower Pan 1/22/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 1/25/2024 Approved CHRISTOPHER WILSON
PLUMBING-Rough 1/25/2024 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 1/29/2024 Approved CHRISTOPHER WILSON
PLUMBING-Rough 2/2/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 2/8/2024 Approved CARLOS MATAMOROS
Green Building Rough 2/8/2024 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 2/8/2024 Approved CARLOS MATAMOROS
Wood Frame 2/8/2024 Approved CARLOS MATAMOROS
Insulation 2/21/2024 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 2/21/2024 Partial Approval CHRISTOPHER WILSON
Insulation 2/27/2024 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 2/27/2024 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 3/20/2024 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 3/20/2024 Approved CHRISTOPHER WILSON
HVAC-Final 11/7/2024 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 11/8/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 11/12/2024 Not Ready for Inspection SEAN HAUPT
HVAC-Final 11/12/2024 Approved SEAN HAUPT
Final 11/13/2024 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 11/13/2024 Approved CHRISTOPHER WILSON
Gas Test 11/13/2024 Approved CHRISTOPHER WILSON
Green Building Final 11/13/2024 Approved CHRISTOPHER WILSON
HVAC-Final 11/13/2024 Approved CHRISTOPHER WILSON
PLUMBING-Final 11/13/2024 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 11/13/2024 SGSOV Approved CHRISTOPHER WILSON
Service/Power Release 11/13/2024 Approved CHRISTOPHER WILSON
Smoke Detectors 11/13/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 11/14/2024 Approved CHRISTOPHER WILSON
Final 12/4/2024 OK to Issue CofO CHRISTOPHER WILSON