4331-4333 S BUDLONG AVE 90037

Certificate Information: 4331-4333 S BUDLONG AVE 90037

Application / Permit
21010-10000-06877
Plan Check / Job No.
B21LA24364
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
PROPOSED 2-CAR GARAGE. 2 OF 3
Permit Issued
Issued on 9/1/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2022 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 FARSHAD ALIMOHAMADI
Corrections Issued 1/18/2022 FARSHAD ALIMOHAMADI
Quality Review Completed 1/19/2022 SAI KHUM
Building Plans Picked Up 1/24/2022 APPLICANT
Applicant returned to address corrections 6/1/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 6/9/2022 FARSHAD ALIMOHAMADI
Issued 9/1/2022 APPLICANT
CofO in Progress 7/1/2024 SABAS ALONSO
Permit Finaled 7/10/2024 DEROLD HAUFF
CofO Issued 7/10/2024 DEROLD HAUFF
Permit Finaled 7/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/3/2022 JEANETTE VONG
Low Impact Development Cleared 3/30/2022 KHAING AYE
Roof/Waste drainage to street Cleared 5/24/2022 JEANETTE VONG
Construction near power lines Cleared 5/26/2022 WALTER RAMIREZ

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 11/22/2022 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 11/23/2022 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/8/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/1/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 6/6/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Approved SABAS ALONSO
PLUMBING-Rough 6/23/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/4/2023 Not Ready for Inspection SABAS ALONSO
Green Building Rough 8/4/2023 Approved SABAS ALONSO
HVAC-Rough 8/4/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/17/2023 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 8/23/2023 Approved SABAS ALONSO
Drywall Nailing 9/21/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Not Ready CRAIG DAVIS
Final 5/22/2024 Corrections Issued SABAS ALONSO
Green Building Final 5/22/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/22/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 5/22/2024 Approved SABAS ALONSO
Smoke Detectors 5/22/2024 Approved SABAS ALONSO
Final 6/12/2024 Not Ready for Inspection SABAS ALONSO
Final 6/14/2024 Corrections Issued SABAS ALONSO
Final 6/27/2024 OK to Issue CofO SABAS ALONSO