927 S BERNAL AVE 90023

Certificate Information: 927 S BERNAL AVE 90023

Application / Permit
21010-10000-06866
Plan Check / Job No.
B21LA24356
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY DETACHED ADU PER LAMC 12.22A.33 (c )-(d) CUGU-Project is a Publically Habitable Space adjacent to a Subject Use.
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
CofO Issued on 3/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 MAHNAZ NOURHASHEMI
Corrections Issued 1/30/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 2/9/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 2/11/2022 APPLICANT
Applicant returned to address corrections 4/8/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 4/28/2022 MAHNAZ NOURHASHEMI
Issued 4/28/2022 APPLICANT
CofO in Progress 11/27/2023 FREDDIE RIVERA
Permit Finaled 3/1/2024 DEROLD HAUFF
CofO Issued 3/1/2024 DEROLD HAUFF
Permit Finaled 3/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/16/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/17/2022 TREVOR QUAN
Sewer availability Cleared 2/17/2022 TREVOR QUAN
ZI Cleared 2/17/2022 DANIEL CORONADO
Clean Up Green Up Cleared 2/23/2022 DANIEL CORONADO
Grading Pre-Inspection Cleared 3/21/2022 KIRK LINKLATER
Hydrant and Access approval Cleared 4/1/2022 DWAYNE LAURENT
GPI Written Notices Cleared 4/8/2022 MAHNAZ NOURHASHEMI
Low Impact Development Cleared 4/14/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 4/27/2022 TREVOR QUAN

Contact Information

Contractor Tech Master Construction Inc; Lic. No.: 1054601-B 18327 GRIDLEY ROAD STE B      CERRITOS, CA 90703
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/10/2022 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 5/11/2022 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 6/6/2022 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/30/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Partial Approval FREDDIE RIVERA
HVAC-Rough 6/30/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 6/30/2022 Approved FREDDIE RIVERA
Pre-Inspection 6/30/2022 Corrections Issued FREDDIE RIVERA
Wood Frame 7/6/2022 Approved FREDDIE RIVERA
Insulation 7/11/2022 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 7/11/2022 Approved FREDDIE RIVERA
Insulation 7/14/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 7/18/2022 Approved FREDDIE RIVERA
Shower Pan 7/18/2022 Approved FREDDIE RIVERA
Drywall Nailing 7/20/2022 Conditional Approval FREDDIE RIVERA
Green Building Rough 7/20/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 9/21/2022 Corrections Issued FREDDIE RIVERA
Service/Power Release 9/21/2022 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/26/2022 Approved FREDDIE RIVERA
Drywall Nailing 9/26/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 9/26/2022 Corrections Issued FREDDIE RIVERA
Final 9/26/2022 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 9/26/2022 Approved FREDDIE RIVERA
Green Building Final 9/26/2022 Corrections Issued FREDDIE RIVERA
MERV13>=Final 9/26/2022 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 9/26/2022 Approved FREDDIE RIVERA
PLUMBING-Final 9/26/2022 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 9/26/2022 Partial Inspection FREDDIE RIVERA
Smoke Detectors 9/26/2022 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 9/26/2022 Approved FREDDIE RIVERA
Gas Test 10/5/2022 Partial Inspection FREDDIE RIVERA
Service/Power Release 10/5/2022 Partial Inspection FREDDIE RIVERA
Final 10/20/2022 Partial Inspection FREDDIE RIVERA
Gas Test 10/20/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 10/20/2022 Partial Inspection FREDDIE RIVERA
MERV13>=Final 10/20/2022 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/20/2022 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 10/20/2022 Partial Inspection FREDDIE RIVERA
Final 10/24/2022 Partial Inspection FREDDIE RIVERA
Gas Test 10/24/2022 Approved FREDDIE RIVERA
Green Building Final 10/24/2022 Corrections Issued FREDDIE RIVERA
MERV13>=Final 10/24/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Approved FREDDIE RIVERA
Service/Power Release 10/24/2022 Approved FREDDIE RIVERA
Final 10/27/2022 Conditional Approval RUBEN SALAS
Green Building Final 10/27/2022 Approved RUBEN SALAS
Special/Order Compliance 11/16/2023 Corrections Issued FREDDIE RIVERA
Final 11/22/2023 OK to Issue CofO FREDDIE RIVERA