1460 W 35TH ST 1-3 90018
Certificate Information: 1460 W 35TH ST 1-3 90018
- Application / Permit
- 21010-10000-06863
- Plan Check / Job No.
- B21LA24331
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 4-STORY DUPLEX WITH ATTACHED ADU (10,247.5 SF) AND ATTCHED 2-CAR GARAGE (349.5 SF) PER LAMC 12.22.A.33(c) AND (e).
- Permit Issued
- Issued on 11/1/2022
- Issuing Office
- Metro
- Current Status
- Issued on 11/1/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | VIVIAN LAO |
| Corrections Issued | 1/20/2022 | VIVIAN LAO |
| Quality Review Completed | 1/26/2022 | KEN GILL |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| Plan Check Approved | 7/11/2022 | VIVIAN LAO |
| Issued | 11/1/2022 | APPLICANT |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 2/8/2022 | MAXFIELD VERMY |
| Address approval | Cleared | 2/16/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2022 | JEANIE LAM |
| Sewer availability | Cleared | 2/17/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 3/9/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/10/2022 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 4/7/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/25/2023 | Partial Inspection | SABAS ALONSO |
| Pre-Inspection | 6/10/2024 | Corrections Issued | JOSEPH MCGARRY |
| Pre-Inspection | 12/27/2024 | Partial Inspection | SABAS ALONSO |
| Pre-Inspection | 7/23/2025 | Partial Inspection | SABAS ALONSO |
| Sewer | 8/22/2025 | Not Ready for Inspection | JOSH MEISTER |
| Underground Mechanical | 8/25/2025 | Partial Approval | JOSH MEISTER |
| Excavation/Setback/Form/Re-Bar | 8/26/2025 | Partial Approval | BRENDAN MORELLI |
| METHANE-Subgrade | 9/4/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 9/22/2025 | Approved | SABAS ALONSO |
| METHANE-Barrier | 9/22/2025 | Approved | SABAS ALONSO |
| Deputy Steel/Welding | 3/16/2026 | Conditional Approval | SABAS ALONSO |
| Structural Steel Frame | 3/18/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2026 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2026 | Partial Approval | JOHN QUINTANILLA |
| Pre-Inspection | 5/7/2026 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Inspection | 5/19/2026 | Partial Approval | LUIS CASTRO |
| Deputy Wood Construction | 6/1/2026 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2026 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 6/22/2026 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 7/2/2026 | Approved | SABAS ALONSO |