858-860 N HUDSON AVE 90038
Certificate Information: 858-860 N HUDSON AVE 90038
- Application / Permit
- 21010-10000-06849
- Plan Check / Job No.
- B21LA24313
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX WITH ATTACHED CARPORT (FRONT)
- Permit Issued
- Issued on 12/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | STARR CHEN |
| Corrections Issued | 2/16/2022 | STARR CHEN |
| Quality Review Completed | 2/17/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 2/23/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 6/8/2022 | APPLICANT |
| Applicant returned to address corrections | 10/5/2022 | STARR CHEN |
| Plan Check Approved | 10/21/2022 | STARR CHEN |
| Issued | 12/2/2022 | APPLICANT |
| CofO in Progress | 9/29/2024 | JEFFREY MEAD |
| Permit Finaled | 11/19/2024 | DEROLD HAUFF |
| CofO Issued | 11/19/2024 | DEROLD HAUFF |
| Permit Finaled | 11/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 2/9/2022 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 2/14/2022 | MAYELA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | CELINA MORENO |
| Low Impact Development | Cleared | 3/15/2022 | SUNG JOON WON |
| Address approval | Cleared | 3/31/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 3/31/2022 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 4/6/2022 | KURT CORRAL |
| Sewer availability | Cleared | 4/7/2022 | CELINA MORENO |
| Trees in Parkway | Cleared | 4/8/2022 | ADALBERTO VERA |
| Construction near power lines | Cleared | 6/22/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 14537 VENTURA BLVD SHERMAN OAKS, CA 91403 |
| Geologist | Kaligi,, Adam Azad; Lic. No.: GEO9287 | 19197 GOLDEN VALLEY RD #709 SANTA CLARITA, CA 91387 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/17/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Underground Mechanical | 1/17/2023 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/6/2023 | Approved | JEFFREY MEAD |
| METHANE-Barrier | 4/6/2023 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 4/6/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/27/2023 | Corrections Issued | LILIANA PORTILLO |
| METHANE-Rough | 4/27/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 4/27/2023 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/2/2023 | Partial Approval | LILIANA PORTILLO |
| Insulation | 5/2/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 5/2/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 6/14/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 11/27/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 11/27/2023 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 11/27/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 11/27/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 11/27/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 11/30/2023 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 11/30/2023 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 12/8/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 12/21/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 12/21/2023 | Partial Approval | JEFFREY MEAD |
| Interior/Exterior Lathing | 2/13/2024 | Approved | AMIR NAZARIAN |
| Shower Pan | 2/13/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Underground Mechanical | 4/25/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 7/25/2024 | Approved | JEFFREY MEAD |
| Final | 7/25/2024 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 7/25/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 7/25/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Not Ready | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/22/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 8/22/2024 | Approved | JEFFREY MEAD |
| Final | 8/22/2024 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 8/22/2024 | Approved | JEFFREY MEAD |
| Green Building Rough | 8/22/2024 | Approved | JEFFREY MEAD |
| HVAC-Final | 8/22/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 8/22/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 8/22/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 8/22/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 9/13/2024 | Approved | JEFFREY MEAD |
| Final | 9/13/2024 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Final | 9/13/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 9/13/2024 | Approved | JEFFREY MEAD |
| Service/Power Release | 9/13/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Special/Order Compliance | 9/18/2024 | Approved | JEFFREY MEAD |
| Final | 9/27/2024 | OK to Issue CofO | JEFFREY MEAD |
| Service/Power Release | 9/27/2024 | Approved | JEFFREY MEAD |