5948 W 74TH ST 90045

Certificate Information: 5948 W 74TH ST 90045

Application / Permit
21010-10000-06847
Plan Check / Job No.
B21LA24312
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 7/29/2022
Issuing Office
Current Status
Issued on 7/29/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/2/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 CARLOS MONTES
Corrections Issued 1/29/2022 CARLOS MONTES
Quality Review Completed 1/31/2022 LIPING TENG
Applicant returned to address corrections 6/24/2022 CARLOS MONTES
Plan Check Approved 7/28/2022 CARLOS MONTES
Issued 7/29/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/1/2022 DINAH GARIN
Miscellaneous Cleared 2/2/2022 SAUL GARCIA
Specific Plan Cleared 2/2/2022 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 2/4/2022 DINAH GARIN
Sewer availability Cleared 2/4/2022 DINAH GARIN
Grading Pre-Inspection Cleared 2/10/2022 ROBERT HUGHES
Construction near power lines Cleared 4/22/2022 RIDWAN HARDY
Low Impact Development Cleared 5/17/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 5/20/2022 JENSON LEE
GPI Written Notices Cleared 7/27/2022 CARLOS MONTES

Contact Information

Contractor Owner-Builder       ,
Engineer Song,, Zhenyu Michael; Lic. No.: S5266 12631 IMPERIAL HWY F-230      SANTA FE SPRINGS, CA 90670

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/6/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 2/13/2023 Approved BOBBY KEY
PLUMBING-Rough 2/22/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/28/2023 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Approved BOBBY KEY
Underground Mechanical 4/11/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 4/20/2023 Partial Approval BOBBY KEY
Sewer 4/20/2023 Approved BOBBY KEY
HVAC-Rough 4/24/2023 Approved BOBBY KEY
PLUMBING-Rough 4/24/2023 Approved BOBBY KEY
Underground Mechanical 4/24/2023 Approved BOBBY KEY
Shower Pan 5/4/2023 Approved BOBBY KEY
Interior/Exterior Lathing 5/19/2023 Partial Approval BOBBY KEY
Interior/Exterior Lathing 6/28/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 7/5/2023 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 7/5/2023 Approved BOBBY KEY
Green Building Rough 7/5/2023 Approved BOBBY KEY
MERV13>=Rough 7/5/2023 Approved BOBBY KEY
Verify Sprinkler Sign Off 7/5/2023 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 8/28/2023 Approved BOBBY KEY
Verify Sprinkler Sign Off 8/28/2023 Approved BOBBY KEY
Insulation 1/16/2024 Approved BOBBY KEY
Drywall Nailing 1/25/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 5/20/2024 Approved BOBBY KEY
ELECTRICAL-Final 12/16/2024 Approved TEMISTOCLES CAAL
Final 12/16/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 12/16/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 12/16/2024 Corrections Issued TEMISTOCLES CAAL
MERV13>=Final 12/16/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 12/16/2024 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Approved TEMISTOCLES CAAL
Service/Power Release 12/16/2024 Not Required TEMISTOCLES CAAL
Smoke Detectors 12/16/2024 Approved TEMISTOCLES CAAL
Gas Test 1/29/2025 Approved TEMISTOCLES CAAL
Green Building Final 1/29/2025 Approved TEMISTOCLES CAAL
HVAC-Final 1/29/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 1/29/2025 Approved TEMISTOCLES CAAL