910-910 1/2 N HUDSON AVE 90038

Certificate Information: 910-910 1/2 N HUDSON AVE 90038

Application / Permit
21010-10000-06842
Plan Check / Job No.
B21LA24308
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX AT FRONT OF LOT.
Permit Issued
Issued on 3/31/2023
Issuing Office
Metro
Current Status
CofO Corrected on 7/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 JAD BASMA
Corrections Issued 2/4/2022 JAD BASMA
Quality Review Completed 2/16/2022 KEN GILL
Building Plans Picked Up 4/22/2022 APPLICANT
Applicant returned to address corrections 12/6/2022 JAD BASMA
Plan Check Approved 12/6/2022 JAD BASMA
Issued 3/31/2023 APPLICANT
CofO in Progress 4/15/2025 JEFFREY MEAD
CofO Issued-Status Void 4/19/2025 DEROLD HAUFF
Permit Finaled-Status Void 4/19/2025 DEROLD HAUFF
Re-Activate Permit 6/16/2025 DEROLD HAUFF
Permit Finaled 7/2/2025 DEROLD HAUFF
CofO Corrected 7/2/2025 DEROLD HAUFF
Permit Finaled 7/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/9/2022 CELINA MORENO
Address approval Cleared 2/9/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/15/2022 CELINA MORENO
Sewer availability Cleared 5/6/2022 CELINA MORENO
Trees in Parkway Cleared 6/2/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 6/9/2022 KURT CORRAL
Frnt yard landscape/Water mgmt Cleared 6/21/2022 RYAN LY
Low Impact Development Cleared 11/21/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 11/29/2022 TREVOR QUAN

Contact Information

Contractor C S W F Construction Inc; Lic. No.: 1021458-B 15831 SAN JOSE AVE      LA PUENTE, CA 91744
Engineer Ivy, Green Construction And Engineering; Lic. No.: C87372 16200 VENTURA BLVD   227    ENCINO, CA 91436

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/6/2023 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 6/6/2023 No Access for Inspection JEFFREY MEAD
METHANE-Barrier 6/6/2023 No Access for Inspection JEFFREY MEAD
METHANE-Subgrade 6/6/2023 No Access for Inspection JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 6/9/2023 Approved JEFFREY MEAD
PLUMBING-Rough 6/29/2023 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Approved JEFFREY MEAD
Insulation 7/6/2023 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 8/2/2023 Partial Approval JEFFREY MEAD
PLUMBING-Rough 10/24/2023 Corrections Issued JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Partial Approval JEFFREY MEAD
PLUMBING-Rough 10/27/2023 Partial Approval JEFFREY MEAD
Insulation 11/9/2023 Corrections Issued JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Approved JEFFREY MEAD
ELECTRICAL-Final 12/19/2023 Partial Approval JEFFREY MEAD
HVAC-Rough 12/19/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 1/10/2024 Not Ready for Inspection JEFFREY MEAD
PLUMBING-Rough 1/10/2024 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 1/17/2024 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 2/1/2024 Conditional Approval JEFFREY MEAD
Green Building Rough 2/1/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 2/1/2024 Approved JEFFREY MEAD
METHANE-Rough 2/1/2024 Approved JEFFREY MEAD
PLUMBING-Rough 2/1/2024 Approved JEFFREY MEAD
Verify Sprinkler Sign Off 2/1/2024 Approved JEFFREY MEAD
Deputy Steel/Welding 2/6/2024 No Access for Inspection AMIR NAZARIAN
Insulation 2/13/2024 Partial Approval AMIR NAZARIAN
Drywall Nailing 2/23/2024 Not Ready for Inspection JEFFREY MEAD
Drywall Nailing 2/26/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 2/26/2024 Approved JEFFREY MEAD
Sewer 5/8/2024 Approved JEFFREY MEAD
Underground Mechanical 7/2/2024 Approved JEFFREY MEAD
ELECTRICAL-Final 3/21/2025 Corrections Issued JEFFREY MEAD
Final 4/1/2025 Corrections Issued JEFFREY MEAD
Final 4/4/2025 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 4/10/2025 Approved JEFFREY MEAD
Final 4/10/2025 Not Ready for Inspection JEFFREY MEAD
Footing/Foundation/Slab 4/10/2025 Approved JEFFREY MEAD
Green Building Final 4/10/2025 Approved JEFFREY MEAD
METHANE-Barrier 4/10/2025 Approved JEFFREY MEAD
METHANE-Subgrade 4/10/2025 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 4/10/2025 SGSOV Approved JEFFREY MEAD
Service/Power Release 4/10/2025 Approved JEFFREY MEAD
Smoke Detectors 4/10/2025 Corrections Issued JEFFREY MEAD
Final 4/14/2025 OK to Issue CofO JEFFREY MEAD
Smoke Detectors 4/14/2025 Approved JEFFREY MEAD