4658 W LOMITA ST 90019
Certificate Information: 4658 W LOMITA ST 90019
- Application / Permit
- 21010-10000-06839
- Plan Check / Job No.
- B21LA24300
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ADU WITH ROOFTOP DECK PER LAMC 12.22 A.33(c) AND (d) (REAR BLDG)
- Permit Issued
- Issued on 1/26/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | KHEDER ALRAZAA |
| Corrections Issued | 2/1/2022 | KHEDER ALRAZAA |
| Quality Review Completed | 2/10/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| Applicant returned to address corrections | 12/14/2022 | KHEDER ALRAZAA |
| Plan Check Approved | 12/20/2022 | KHEDER ALRAZAA |
| Issued | 1/26/2023 | APPLICANT |
| CofO in Progress | 9/17/2024 | JUSTIN HAWLEY |
| CofO Issued | 9/24/2024 | RUBEN SALAS |
| Permit Finaled | 9/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 1/24/2022 | RYAN LY |
| Address approval | Cleared | 1/26/2022 | CHRISTOPHER ROCHA |
| Highway dedication | Cleared | 1/26/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 2/9/2022 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 3/26/2022 | PATRICK MAGALLANES |
| Hydrant and Access approval | Cleared | 6/9/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 12/6/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 12/14/2022 | AMAAN MALIK |
Contact Information
| Contractor | Safe Quake Construction; Lic. No.: 571102-B | 2088 S ATLANTIC BL #291 MONTEREY PARK, CA 91754 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/13/2023 | Not Ready for Inspection | CALEB MEISTER |
| Footing/Foundation/Slab | 4/13/2023 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Barrier | 4/13/2023 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Subgrade | 4/13/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 4/18/2023 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 5/11/2023 | Approved | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 5/12/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Not Ready for Inspection | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Partial Approval | CALEB MEISTER |
| Insulation | 5/23/2023 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 10/4/2023 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 10/4/2023 | Partial Approval | SCOTT FINNILA |
| METHANE-Rough | 10/4/2023 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 10/4/2023 | Not Ready for Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 11/22/2023 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 11/22/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 11/22/2023 | Approved | JUSTIN HAWLEY |
| Wood Frame | 11/22/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 11/28/2023 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 11/28/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 11/28/2023 | Partial Approval | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 11/28/2023 | Approved | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 11/28/2023 | Approved | JUSTIN HAWLEY |
| Insulation | 12/1/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 12/26/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 12/26/2023 | Approved | BRENDAN MORELLI |
| Sewer | 4/2/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/18/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 7/18/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 7/18/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 8/8/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 8/8/2024 | Corrections Issued | JUSTIN HAWLEY |
| Gas Test | 8/8/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Final | 8/8/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Final | 8/8/2024 | Approved | JUSTIN HAWLEY |
| Smoke Detectors | 8/8/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 8/9/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Gas Test | 8/9/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 8/9/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 8/9/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 8/13/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Gas Test | 8/13/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 8/13/2024 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Final | 8/13/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 8/14/2024 | Approved | JUSTIN HAWLEY |
| Final | 8/14/2024 | Corrections Issued | JUSTIN HAWLEY |
| Gas Test | 8/14/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Final | 8/14/2024 | Approved | JUSTIN HAWLEY |
| Gas Test | 8/27/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 8/27/2024 | Corrections Issued | JUSTIN HAWLEY |
| Final | 9/11/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 9/11/2024 | Approved | JUSTIN HAWLEY |
| Green Building Final | 9/11/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Service/Power Release | 9/11/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 9/17/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| Green Building Final | 9/17/2024 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 9/17/2024 | Not Required | JUSTIN HAWLEY |