1469 E 22ND ST 90011
Certificate Information: 1469 E 22ND ST 90011
- Application / Permit
- 21010-10000-06832
- Plan Check / Job No.
- B21LA24293
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) 4-CAR GARAGE
- Permit Issued
- Issued on 1/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | DANIEL YIP |
| Corrections Issued | 1/19/2022 | DANIEL YIP |
| Quality Review Completed | 1/19/2022 | KEN GILL |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| Applicant returned to address corrections | 3/25/2022 | DANIEL YIP |
| Applicant returned to address corrections | 4/13/2022 | DANIEL YIP |
| Plan Check Approved | 8/4/2022 | DANIEL YIP |
| Issued | 1/5/2023 | APPLICANT |
| CofO in Progress | 10/12/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 12/19/2024 | DEROLD HAUFF |
| CofO Issued | 12/19/2024 | DEROLD HAUFF |
| Permit Finaled | 12/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 8/3/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 8/4/2022 | CHRIS VONG |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/25/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 2/27/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Rough | 2/27/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Insulation | 2/27/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 2/27/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/3/2023 | Corrections Issued | BRENDAN MORELLI |
| Insulation | 3/3/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 3/3/2023 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 5/26/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/26/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 5/26/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/26/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/26/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 6/1/2023 | Conditional Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 6/1/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 6/1/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Rough | 6/12/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 6/12/2023 | Partial Approval | BRENDAN MORELLI |
| Insulation | 6/16/2023 | Approved | RUBEN SALAS |
| Drywall Nailing | 6/28/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Drywall Nailing | 7/10/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 10/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/11/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/11/2024 | Approved | ALEJANDRO DE ARTOLA |