1471 E 22ND ST 90011

Certificate Information: 1471 E 22ND ST 90011

Application / Permit
21010-10000-06831
Plan Check / Job No.
B21LA24293
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 1/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 DANIEL YIP
Corrections Issued 1/19/2022 DANIEL YIP
Quality Review Completed 1/19/2022 KEN GILL
Building Plans Picked Up 1/24/2022 APPLICANT
Applicant returned to address corrections 3/25/2022 DANIEL YIP
Applicant returned to address corrections 4/13/2022 DANIEL YIP
Plan Check Approved 8/4/2022 DANIEL YIP
Issued 1/5/2023 APPLICANT
CofO in Progress 10/16/2024 JOHN QUINTANILLA
Permit Finaled 12/10/2024 DEROLD HAUFF
CofO Issued 12/10/2024 DEROLD HAUFF
Permit Finaled 12/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/26/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/27/2022 JEANIE LAM
Sewer availability Cleared 3/8/2022 AMY SHUM
Low Impact Development Cleared 5/17/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 7/29/2022 JEANIE LAM

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/25/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 2/27/2023 Corrections Issued BRENDAN MORELLI
Green Building Rough 2/27/2023 Not Ready for Inspection BRENDAN MORELLI
Insulation 2/27/2023 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Rough 2/27/2023 Not Ready for Inspection BRENDAN MORELLI
Verify Sprinkler Sign Off 2/27/2023 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 3/3/2023 Corrections Issued BRENDAN MORELLI
Insulation 3/3/2023 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Rough 3/3/2023 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Partial Approval BRENDAN MORELLI
Green Building Rough 3/8/2023 Not Ready for Inspection BRENDAN MORELLI
Insulation 3/8/2023 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 3/8/2023 Not Ready for Inspection BRENDAN MORELLI
Verify Sprinkler Sign Off 3/8/2023 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 5/26/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/26/2023 Approved ALIZAH MAYAGOITIA
Green Building Rough 5/26/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 5/26/2023 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 5/26/2023 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 5/26/2023 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 5/26/2023 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 6/1/2023 Approved BRENDAN MORELLI
HVAC-Rough 6/1/2023 Approved BRENDAN MORELLI
Green Building Rough 6/12/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 6/12/2023 Partial Approval BRENDAN MORELLI
Insulation 6/16/2023 Approved RUBEN SALAS
Drywall Nailing 6/28/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 10/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/11/2024 Approved ALEJANDRO DE ARTOLA
Gas Test 10/11/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 10/11/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 10/11/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/15/2024 Approved JOHN QUINTANILLA
Final 10/15/2024 OK to Issue CofO JOHN QUINTANILLA
Green Building Final 10/15/2024 Approved JOHN QUINTANILLA
HVAC-Final 10/15/2024 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 10/15/2024 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 10/15/2024 Approved JOHN QUINTANILLA
Smoke Detectors 10/15/2024 Approved JOHN QUINTANILLA