Excavation/Setback/Form/Re-Bar
|
6/22/2023
|
Not Ready for Inspection
|
DAVID FEILER
|
|
Footing/Foundation/Slab
|
6/22/2023
|
Not Ready for Inspection
|
DAVID FEILER
|
|
METHANE-Barrier
|
6/22/2023
|
Not Ready for Inspection
|
DAVID FEILER
|
|
METHANE-Subgrade
|
6/22/2023
|
Corrections Issued
|
DAVID FEILER
|
|
Excavation/Setback/Form/Re-Bar
|
6/28/2023
|
Corrections Issued
|
CLAYTON GRAHAM
|
|
METHANE-Barrier
|
6/28/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
METHANE-Subgrade
|
6/28/2023
|
Corrections Issued
|
CLAYTON GRAHAM
|
|
Sewer
|
6/28/2023
|
Corrections Issued
|
CLAYTON GRAHAM
|
|
Excavation/Setback/Form/Re-Bar
|
7/3/2023
|
Approved
|
CLAYTON GRAHAM
|
|
Footing/Foundation/Slab
|
7/3/2023
|
Partial Approval
|
CLAYTON GRAHAM
|
|
BUILDING-Rough-Frame
|
7/20/2023
|
Corrections Issued
|
CLAYTON GRAHAM
|
|
Insulation
|
7/20/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
PLUMBING-Rough
|
7/20/2023
|
Corrections Issued
|
CLAYTON GRAHAM
|
|
BUILDING-Rough-Frame
|
7/31/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/31/2023
|
Partial Approval
|
CLAYTON GRAHAM
|
|
Green Building Rough
|
7/31/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
METHANE-Rough
|
7/31/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
Verify Sprinkler Sign Off
|
7/31/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
Footing/Foundation/Slab
|
8/8/2023
|
Partial Approval
|
CLAYTON GRAHAM
|
|
METHANE-Barrier
|
8/8/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
METHANE-Subgrade
|
8/8/2023
|
Approved
|
CLAYTON GRAHAM
|
|
METHANE-Barrier
|
8/9/2023
|
Approved
|
CLAYTON GRAHAM
|
|
Sewer
|
8/15/2023
|
Conditional Approval
|
DAVID FEILER
|
|
Sewer
|
8/23/2023
|
Partial Approval
|
CLAYTON GRAHAM
|
|
BUILDING-Rough-Frame
|
10/17/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/17/2023
|
Corrections Issued
|
CLAYTON GRAHAM
|
|
Green Building Rough
|
10/17/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
METHANE-Rough
|
10/17/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
Verify Sprinkler Sign Off
|
10/17/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/18/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
Wood Frame
|
10/18/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
BUILDING-Rough-Frame
|
10/24/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/24/2023
|
Partial Approval
|
CLAYTON GRAHAM
|
|
Green Building Rough
|
10/24/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
METHANE-Rough
|
10/24/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
Verify Sprinkler Sign Off
|
10/24/2023
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/2/2023
|
Partial Approval
|
ARAM AVEDISIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/6/2023
|
Corrections Issued
|
OGANES TARAKHCHYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/15/2023
|
Corrections Issued
|
OGANES TARAKHCHYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/27/2023
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/5/2024
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
HVAC-Rough
|
1/26/2024
|
Corrections Issued
|
OGANES TARAKHCHYAN
|
|
Deputy Wood Construction
|
2/20/2024
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
ELECTRICAL-Rough
|
2/22/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
PLUMBING-Rough
|
2/22/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
ELECTRICAL-Rough
|
2/26/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/26/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
HVAC-Rough
|
2/26/2024
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
METHANE-Rough
|
2/26/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
PLUMBING-Rough
|
2/26/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
BUILDING-Rough-Frame
|
3/11/2024
|
Corrections Issued
|
JESUS PINEDA
|
|
Green Building Rough
|
3/11/2024
|
Approved
|
JESUS PINEDA
|
|
HVAC-Rough
|
3/11/2024
|
Approved
|
JESUS PINEDA
|
|
Interior/Exterior Lathing
|
3/11/2024
|
Partial Approval
|
JESUS PINEDA
|
|
Verify Sprinkler Sign Off
|
3/11/2024
|
Not Ready for Inspection
|
JESUS PINEDA
|
|
BUILDING-Rough-Frame
|
3/15/2024
|
Corrections Issued
|
OGANES TARAKHCHYAN
|
|
Interior/Exterior Lathing
|
3/15/2024
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Verify Sprinkler Sign Off
|
3/15/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
BUILDING-Rough-Frame
|
3/19/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
Insulation
|
3/19/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
Drywall Nailing
|
4/1/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
Shower Pan
|
4/1/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
Interior/Exterior Lathing
|
4/12/2024
|
Approved
|
OGANES TARAKHCHYAN
|
|
Grounding or Bonding
|
7/9/2024
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
Rough-Elec/Plmb/HVAC
|
7/9/2024
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
Underground Mechanical
|
7/9/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
Underground Mechanical
|
7/11/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
ELECTRICAL-Final
|
8/2/2024
|
Corrections Issued
|
KIRK SANDERS
|
|
Service/Power Release
|
8/2/2024
|
Not Ready for Inspection
|
KIRK SANDERS
|
|
ELECTRICAL-Final
|
8/7/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
PLUMBING-Final
|
8/7/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
PLUMBING-Final
|
8/14/2024
|
Approved
|
DANIEL VERA
|
|
HVAC-Final
|
8/29/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
ELECTRICAL-Final
|
11/6/2024
|
No Access for Inspection
|
ASHLEY THOMPSON
|
|
Service/Power Release
|
11/6/2024
|
No Access for Inspection
|
ASHLEY THOMPSON
|
|
ELECTRICAL-Final
|
11/8/2024
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
Service/Power Release
|
11/8/2024
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
ELECTRICAL-Final
|
11/20/2024
|
Approved
|
ASHLEY THOMPSON
|
|
Service/Power Release
|
11/20/2024
|
Approved
|
ASHLEY THOMPSON
|
|
ELECTRICAL-Final
|
11/22/2024
|
No Access for Inspection
|
ASHLEY THOMPSON
|
|
Final
|
3/3/2025
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
Footing/Foundation/Slab
|
3/3/2025
|
Approved
|
ASHLEY THOMPSON
|
|
Green Building Final
|
3/3/2025
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
SGSOV-Seismic Gas S/O Valve
|
3/3/2025
|
SGSOV Not Ready
|
ASHLEY THOMPSON
|
|
Smoke Detectors
|
3/3/2025
|
Approved
|
ASHLEY THOMPSON
|
|
Final
|
12/8/2025
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
HVAC-Final
|
12/8/2025
|
Approved
|
ASHLEY THOMPSON
|
|
Verify Rec and Parks Fee Memo
|
12/8/2025
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
Gas Test
|
12/12/2025
|
Approved
|
ASHLEY THOMPSON
|
|
Final
|
2/6/2026
|
Conditional Approval
|
ASHLEY THOMPSON
|
|
Green Building Final
|
2/6/2026
|
Approved
|
ASHLEY THOMPSON
|
|
SGSOV-Seismic Gas S/O Valve
|
2/6/2026
|
SGSOV Approved
|
ASHLEY THOMPSON
|