10156-10158 W REGENT ST 90034

Certificate Information: 10156-10158 W REGENT ST 90034

Application / Permit
21010-10000-06829
Plan Check / Job No.
B21LA24291
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH AN ATTACHED 1-CAR GARAGE (REAR BLDG)
Permit Issued
Issued on 2/8/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 KHEDER ALRAZAA
Corrections Issued 2/3/2022 KHEDER ALRAZAA
Quality Review Completed 2/11/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 2/25/2022 APPLICANT
Applicant returned to address corrections 12/14/2022 KHEDER ALRAZAA
Plan Check Approved 1/27/2023 KHEDER ALRAZAA
Issued 2/8/2023 APPLICANT
Permit Finaled 2/17/2026 RICHARD STEINBACH
CofO Issued 2/17/2026 RICHARD STEINBACH
Permit Finaled 2/17/2026 RICHARD STEINBACH

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 2/9/2022 MAYELA VILLA
Address approval Cleared 2/10/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 3/2/2022 DINAH GARIN
Sewer availability Cleared 3/2/2022 DINAH GARIN
Low Impact Development Cleared 4/5/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/8/2022 DINAH GARIN
Hydrant and Access approval Cleared 4/18/2022 JOHN CONNEALLY
GPI Written Notices Cleared 12/14/2022 KHEDER ALRAZAA
Grading Pre-Inspection Cleared 12/14/2022 KHEDER ALRAZAA
Specific Plan Cleared 12/14/2022 KYLE WINSTON
Specific Plan Cleared 1/5/2023 FREDDY GARCIA
Specific Plan Cleared 1/5/2023 FREDDY GARCIA
Highway dedication Cleared 1/19/2023 RAYMOND MUGAMBWA
Miscellaneous Cleared 1/26/2023 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/22/2023 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 6/22/2023 Not Ready for Inspection DAVID FEILER
METHANE-Barrier 6/22/2023 Not Ready for Inspection DAVID FEILER
METHANE-Subgrade 6/22/2023 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 6/28/2023 Corrections Issued CLAYTON GRAHAM
METHANE-Barrier 6/28/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Subgrade 6/28/2023 Corrections Issued CLAYTON GRAHAM
Sewer 6/28/2023 Corrections Issued CLAYTON GRAHAM
Excavation/Setback/Form/Re-Bar 7/3/2023 Approved CLAYTON GRAHAM
Footing/Foundation/Slab 7/3/2023 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 7/20/2023 Corrections Issued CLAYTON GRAHAM
Insulation 7/20/2023 Not Ready for Inspection CLAYTON GRAHAM
PLUMBING-Rough 7/20/2023 Corrections Issued CLAYTON GRAHAM
BUILDING-Rough-Frame 7/31/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Partial Approval CLAYTON GRAHAM
Green Building Rough 7/31/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Rough 7/31/2023 Not Ready for Inspection CLAYTON GRAHAM
Verify Sprinkler Sign Off 7/31/2023 Not Ready for Inspection CLAYTON GRAHAM
Footing/Foundation/Slab 8/8/2023 Partial Approval CLAYTON GRAHAM
METHANE-Barrier 8/8/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Subgrade 8/8/2023 Approved CLAYTON GRAHAM
METHANE-Barrier 8/9/2023 Approved CLAYTON GRAHAM
Sewer 8/15/2023 Conditional Approval DAVID FEILER
Sewer 8/23/2023 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 10/17/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Corrections Issued CLAYTON GRAHAM
Green Building Rough 10/17/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Rough 10/17/2023 Not Ready for Inspection CLAYTON GRAHAM
Verify Sprinkler Sign Off 10/17/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Not Ready for Inspection CLAYTON GRAHAM
Wood Frame 10/18/2023 Not Ready for Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 10/24/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval CLAYTON GRAHAM
Green Building Rough 10/24/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Rough 10/24/2023 Not Ready for Inspection CLAYTON GRAHAM
Verify Sprinkler Sign Off 10/24/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 1/26/2024 Corrections Issued OGANES TARAKHCHYAN
Deputy Wood Construction 2/20/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/22/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 2/22/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/26/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/26/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 2/26/2024 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Rough 2/26/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 2/26/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/11/2024 Corrections Issued JESUS PINEDA
Green Building Rough 3/11/2024 Approved JESUS PINEDA
HVAC-Rough 3/11/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 3/11/2024 Partial Approval JESUS PINEDA
Verify Sprinkler Sign Off 3/11/2024 Not Ready for Inspection JESUS PINEDA
BUILDING-Rough-Frame 3/15/2024 Corrections Issued OGANES TARAKHCHYAN
Interior/Exterior Lathing 3/15/2024 Partial Approval OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 3/15/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/19/2024 Approved OGANES TARAKHCHYAN
Insulation 3/19/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/1/2024 Approved OGANES TARAKHCHYAN
Shower Pan 4/1/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/12/2024 Approved OGANES TARAKHCHYAN
Grounding or Bonding 7/9/2024 Not Ready for Inspection ASHLEY THOMPSON
Rough-Elec/Plmb/HVAC 7/9/2024 Not Ready for Inspection ASHLEY THOMPSON
Underground Mechanical 7/9/2024 Corrections Issued ASHLEY THOMPSON
Underground Mechanical 7/11/2024 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 8/2/2024 Corrections Issued KIRK SANDERS
Service/Power Release 8/2/2024 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 8/7/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 8/7/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 8/14/2024 Approved DANIEL VERA
HVAC-Final 8/29/2024 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 11/6/2024 No Access for Inspection ASHLEY THOMPSON
Service/Power Release 11/6/2024 No Access for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 11/8/2024 Not Ready for Inspection ASHLEY THOMPSON
Service/Power Release 11/8/2024 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 11/20/2024 Approved ASHLEY THOMPSON
Service/Power Release 11/20/2024 Approved ASHLEY THOMPSON
ELECTRICAL-Final 11/22/2024 No Access for Inspection ASHLEY THOMPSON
Final 3/3/2025 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 3/3/2025 Approved ASHLEY THOMPSON
Green Building Final 3/3/2025 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 3/3/2025 SGSOV Not Ready ASHLEY THOMPSON
Smoke Detectors 3/3/2025 Approved ASHLEY THOMPSON
Final 12/8/2025 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Final 12/8/2025 Approved ASHLEY THOMPSON
Verify Rec and Parks Fee Memo 12/8/2025 Not Ready for Inspection ASHLEY THOMPSON
Gas Test 12/12/2025 Approved ASHLEY THOMPSON
Final 2/6/2026 Conditional Approval ASHLEY THOMPSON
Green Building Final 2/6/2026 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Approved ASHLEY THOMPSON