8227 S WESTLAWN AVE 90045

Certificate Information: 8227 S WESTLAWN AVE 90045

Application / Permit
21010-10000-06794
Plan Check / Job No.
B21LA24236
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
1-STORY GARAGE WITH ATTACHED STORAGE AND REC. ROOM
Permit Issued
Issued on 12/15/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2022 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 MAHNAZ NOURHASHEMI
Corrections Issued 1/21/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 2/11/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 2/15/2022 APPLICANT
Plan Check Approved 6/2/2022 MAHNAZ NOURHASHEMI
Issued 12/15/2022 APPLICANT
CofO in Progress 4/19/2025 DAVID FEILER
Permit Finaled 4/21/2025 RICHARD STEINBACH
CofO Issued 4/21/2025 RICHARD STEINBACH
Permit Finaled 4/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Public Works-Highway Ded. Cleared 2/10/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 2/14/2022 HISASHI KOBAYAKAWA
Specific Plan Cleared 2/22/2022 VALERIA CEJA
Hydrant and Access approval Cleared 3/5/2022 CINDY JOSSELYN
Trees in Parkway Cleared 3/24/2022 MAHNAZ NOURHASHEMI
Low Impact Development Cleared 5/19/2022 JULIAN SUNG
Permit Cleared 5/23/2022 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 5/23/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor Imbuia Construction Inc; Lic. No.: 796602-B 4751 DEL MORENO DR      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/31/2023 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 5/31/2023 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Approved BOBBY KEY
Footing/Foundation/Slab 7/11/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 3/13/2024 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 3/13/2024 Approved BOBBY KEY
Green Building Rough 3/13/2024 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 3/22/2024 Approved BOBBY KEY
Green Building Rough 3/22/2024 Approved BOBBY KEY
Interior/Exterior Lathing 3/22/2024 Approved BOBBY KEY
Drywall Nailing 5/23/2024 Not Ready for Inspection BOBBY KEY
Drywall Nailing 5/28/2024 Approved BOBBY KEY
Insulation 5/28/2024 Approved BOBBY KEY
PLUMBING-Final 5/28/2024 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 10/8/2024 Approved BOBBY KEY
ELECTRICAL-Final 4/8/2025 Approved JESUS PINEDA
Final 4/8/2025 Corrections Issued JESUS PINEDA
Green Building Final 4/8/2025 Approved JESUS PINEDA
HVAC-Final 4/8/2025 Partial Inspection JESUS PINEDA
PLUMBING-Final 4/8/2025 Partial Inspection JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Approved JESUS PINEDA
Service/Power Release 4/8/2025 Not Required JESUS PINEDA
Smoke Detectors 4/8/2025 Approved JESUS PINEDA
Final 4/19/2025 OK to Issue CofO DAVID FEILER