8227 S WESTLAWN AVE 90045

Certificate Information: 8227 S WESTLAWN AVE 90045

Application / Permit
21010-10000-06793
Plan Check / Job No.
B21LA24236
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 12/15/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2022 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 MAHNAZ NOURHASHEMI
Corrections Issued 1/21/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 2/11/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 2/15/2022 APPLICANT
Plan Check Approved 6/2/2022 MAHNAZ NOURHASHEMI
Issued 12/15/2022 APPLICANT
CofO in Progress 4/19/2025 DAVID FEILER
Permit Finaled 4/21/2025 RICHARD STEINBACH
CofO Issued 4/21/2025 RICHARD STEINBACH
Permit Finaled 4/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/14/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 2/14/2022 HISASHI KOBAYAKAWA
Permit Cleared 2/22/2022 HISASHI KOBAYAKAWA
Specific Plan Cleared 2/22/2022 VALERIA CEJA
Hydrant and Access approval Cleared 3/5/2022 CINDY JOSSELYN
Low Impact Development Cleared 5/19/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 5/23/2022 HISASHI KOBAYAKAWA

Contact Information

Architect Hamilton,, John Patrick; Lic. No.: C28865 12240 VENICE BLVD SUITE 25      LOS ANGELES, CA 90066
Contractor Imbuia Construction Inc; Lic. No.: 796602-B 4751 DEL MORENO DR      WOODLAND HILLS, CA 91364
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 4/28/2023 Conditional Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 5/31/2023 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 6/16/2023 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 6/16/2023 Corrections Issued BOBBY KEY
Underground Mechanical 6/22/2023 Partial Approval BOBBY KEY
Footing/Foundation/Slab 7/6/2023 Partial Approval BOBBY KEY
Footing/Foundation/Slab 7/28/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Corrections Issued BOBBY KEY
Deputy Wood Construction 12/11/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Approved BOBBY KEY
Deputy Wood Construction 1/3/2024 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Partial Approval BOBBY KEY
Deputy Steel/Welding 1/30/2024 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 3/13/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/13/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 3/13/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 3/18/2024 Conditional Approval BOBBY KEY
HVAC-Rough 3/18/2024 Conditional Approval BOBBY KEY
Special/Order Compliance 3/18/2024 Corrections Issued BOBBY KEY
Verify Sprinkler Sign Off 3/18/2024 Approved BOBBY KEY
Interior/Exterior Lathing 3/22/2024 Partial Approval BOBBY KEY
HVAC-Rough 4/17/2024 Corrections Issued HERBERT GIRON
Insulation 4/17/2024 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 4/25/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Approved JESUS RODRIGUEZ
Green Building Rough 4/25/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 4/25/2024 Approved JESUS RODRIGUEZ
Deputy Wood Construction 4/26/2024 Conditional Approval RICHARD STEINBACH
Shower Pan 5/16/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 5/23/2024 Not Ready for Inspection BOBBY KEY
Drywall Nailing 5/28/2024 Approved BOBBY KEY
PLUMBING-Final 5/28/2024 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 5/31/2024 Approved BOBBY KEY
Underground Mechanical 8/30/2024 Approved BOBBY KEY
Gas Test 9/18/2024 Approved BOBBY KEY
Sewer 9/18/2024 Approved BOBBY KEY
Underground Mechanical 9/18/2024 Approved BOBBY KEY
ELECTRICAL-Final 10/8/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 10/9/2024 Partial Approval BOBBY KEY
ELECTRICAL-Final 10/18/2024 Corrections Issued BOBBY KEY
HVAC-Final 10/18/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 10/18/2024 Not Ready for Inspection BOBBY KEY
HVAC-Final 11/5/2024 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Final 11/5/2024 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 4/8/2025 Approved JESUS PINEDA
Final 4/8/2025 Corrections Issued JESUS PINEDA
Green Building Final 4/8/2025 Approved JESUS PINEDA
HVAC-Final 4/8/2025 Approved JESUS PINEDA
PLUMBING-Final 4/8/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Approved JESUS PINEDA
Service/Power Release 4/8/2025 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 4/8/2025 Approved JESUS PINEDA
Final 4/19/2025 OK to Issue CofO DAVID FEILER
Service/Power Release 4/19/2025 Approved DAVID FEILER