8227 S WESTLAWN AVE 90045
Certificate Information: 8227 S WESTLAWN AVE 90045
- Application / Permit
- 21010-10000-06793
- Plan Check / Job No.
- B21LA24236
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 12/15/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/21/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 2/11/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| Plan Check Approved | 6/2/2022 | MAHNAZ NOURHASHEMI |
| Issued | 12/15/2022 | APPLICANT |
| CofO in Progress | 4/19/2025 | DAVID FEILER |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
| CofO Issued | 4/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/14/2022 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 2/22/2022 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 2/22/2022 | VALERIA CEJA |
| Hydrant and Access approval | Cleared | 3/5/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 5/19/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 5/23/2022 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Hamilton,, John Patrick; Lic. No.: C28865 | 12240 VENICE BLVD SUITE 25 LOS ANGELES, CA 90066 |
| Contractor | Imbuia Construction Inc; Lic. No.: 796602-B | 4751 DEL MORENO DR WOODLAND HILLS, CA 91364 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 4/28/2023 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 5/31/2023 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 6/16/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 6/16/2023 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 6/22/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 7/6/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 7/28/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Corrections Issued | BOBBY KEY |
| Deputy Wood Construction | 12/11/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2023 | Approved | BOBBY KEY |
| Deputy Wood Construction | 1/3/2024 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Partial Approval | BOBBY KEY |
| Deputy Steel/Welding | 1/30/2024 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 3/13/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 3/13/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 3/18/2024 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 3/18/2024 | Conditional Approval | BOBBY KEY |
| Special/Order Compliance | 3/18/2024 | Corrections Issued | BOBBY KEY |
| Verify Sprinkler Sign Off | 3/18/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 3/22/2024 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 4/17/2024 | Corrections Issued | HERBERT GIRON |
| Insulation | 4/17/2024 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/25/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 4/25/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 4/25/2024 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 4/26/2024 | Conditional Approval | RICHARD STEINBACH |
| Shower Pan | 5/16/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 5/23/2024 | Not Ready for Inspection | BOBBY KEY |
| Drywall Nailing | 5/28/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 5/28/2024 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 5/31/2024 | Approved | BOBBY KEY |
| Underground Mechanical | 8/30/2024 | Approved | BOBBY KEY |
| Gas Test | 9/18/2024 | Approved | BOBBY KEY |
| Sewer | 9/18/2024 | Approved | BOBBY KEY |
| Underground Mechanical | 9/18/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/8/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 10/9/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 10/18/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 10/18/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 10/18/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 11/5/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 11/5/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/8/2025 | Approved | JESUS PINEDA |
| Final | 4/8/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 4/8/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 4/8/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 4/8/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/8/2025 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 4/8/2025 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 4/8/2025 | Approved | JESUS PINEDA |
| Final | 4/19/2025 | OK to Issue CofO | DAVID FEILER |
| Service/Power Release | 4/19/2025 | Approved | DAVID FEILER |