1309 1/2 W GAGE AVE 90044
Certificate Information: 1309 1/2 W GAGE AVE 90044
- Application / Permit
- 21010-10000-06788
- Plan Check / Job No.
- B21LA24206
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU
- Permit Issued
- Issued on 7/26/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2022 | JESSE JIMENEZ |
| Corrections Issued | 1/12/2022 | JESSE JIMENEZ |
| Building Plans Picked Up | 1/14/2022 | APPLICANT |
| Plan Check Approved | 7/11/2023 | FERNANDO FLORES |
| Issued | 7/26/2023 | APPLICANT |
| CofO in Progress | 7/29/2024 | JOSE MACIAS |
| Permit Finaled | 7/29/2024 | DEROLD HAUFF |
| CofO Issued | 7/29/2024 | DEROLD HAUFF |
| Permit Finaled | 7/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/17/2022 | RIDWAN HARDY |
| Address approval | Cleared | 1/12/2023 | WALLIE JONG |
| Low Impact Development | Cleared | 4/7/2023 | TOMMY YIN |
| Tenant Habitability Plan | Cleared | 4/7/2023 | RICARDO BOHORQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2023 | WALLIE JONG |
| Sewer availability | Cleared | 4/11/2023 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 4/27/2023 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/26/2023 | Partial Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 11/8/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 11/8/2023 | Partial Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 11/9/2023 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2023 | Partial Approval | CRAIG DAVIS |
| PLUMBING-Rough | 12/4/2023 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 12/4/2023 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 12/8/2023 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 12/8/2023 | Not Ready for Inspection | DAVID FEILER |
| Sewer | 12/8/2023 | Partial Approval | DAVID FEILER |
| Wood Frame | 12/8/2023 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 12/18/2023 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Approved | CRAIG DAVIS |
| PLUMBING-Rough | 12/18/2023 | Approved | CRAIG DAVIS |
| Sewer | 12/18/2023 | Partial Approval | CRAIG DAVIS |
| Wood Frame | 12/18/2023 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 12/19/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Masonry Wall/Backfill | 12/19/2023 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/19/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Sewer | 12/19/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Wood Frame | 12/19/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Insulation | 1/31/2024 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 2/12/2024 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 2/12/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 2/12/2024 | Approved | SABAS ALONSO |
| Sewer | 2/12/2024 | Corrections Issued | SABAS ALONSO |
| Wood Frame | 2/12/2024 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/20/2024 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/20/2024 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2024 | Approved | BRENDAN MORELLI |
| Green Building Rough | 2/20/2024 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 2/20/2024 | Approved | BRENDAN MORELLI |
| Insulation | 2/20/2024 | Approved | BRENDAN MORELLI |
| Sewer | 2/20/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 2/20/2024 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 3/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/12/2024 | Partial Approval | JOSH MEISTER |
| Sewer | 3/12/2024 | No Access for Inspection | JOSH MEISTER |
| Final | 5/13/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 5/13/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 5/13/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Service/Power Release | 5/13/2024 | Corrections Issued | CRAIG DAVIS |
| Smoke Detectors | 5/13/2024 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Pre-Inspection | 5/24/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 6/4/2024 | Partial Inspection | CRAIG DAVIS |
| Green Building Final | 6/4/2024 | Partial Approval | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Service/Power Release | 6/4/2024 | Partial Inspection | CRAIG DAVIS |
| Final | 6/27/2024 | Corrections Issued | DAVID FEILER |
| Green Building Final | 6/27/2024 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Not Ready | DAVID FEILER |
| Service/Power Release | 6/27/2024 | Not Ready for Inspection | DAVID FEILER |
| Final | 7/22/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 7/22/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 7/22/2024 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 7/22/2024 | Corrections Issued | JOSE MACIAS |
| Sewer | 7/22/2024 | Approved | JOSE MACIAS |
| Final | 7/26/2024 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 7/26/2024 | Approved | JOSE MACIAS |