14210 W GILMORE ST 91401

Certificate Information: 14210 W GILMORE ST 91401

Application / Permit
21010-10000-06773
Plan Check / Job No.
B21LA24191
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD W/ ATTACHED REC ROOM AT FRONT OF LOT. 1 OF 3
Permit Issued
Issued on 7/6/2023
Issuing Office
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2021 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 SERGIO GUTIERREZ
Corrections Issued 1/11/2022 SERGIO GUTIERREZ
Quality Review Completed 1/13/2022 FARUK SEZER
Building Plans Picked Up 1/18/2022 APPLICANT
Applicant returned to address corrections 4/3/2023 SERGIO GUTIERREZ
Plan Check Approved 6/8/2023 SERGIO GUTIERREZ
Issued 7/6/2023 APPLICANT
CofO in Progress 7/20/2024 RYAN SALAZAR
Permit Finaled 8/5/2024 RUBEN SALAS
CofO Issued 8/5/2024 RUBEN SALAS
Permit Finaled 8/5/2024 RUBEN SALAS

Permit Application Clearance Information

"Q" conditions Cleared 1/20/2022 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 3/8/2022 DAGOVERTO GUERRERO
Frnt yard landscape/Water mgmt Cleared 3/8/2022 DANIEL CORONADO
Highway dedication Cleared 3/8/2022 DAGOVERTO GUERRERO
Permit Cleared 3/8/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/8/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 4/8/2022 KURT CORRAL
Low Impact Development Cleared 2/13/2023 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 2/22/2023 DAGOVERTO GUERRERO
Address approval Cleared 4/18/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/3/2023 Partial Approval DAVID MATSON
Underground Mechanical 8/3/2023 Not Ready for Inspection DAVID MATSON
Footing/Foundation/Slab 8/14/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/29/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Approval RYAN SALAZAR
Underground Mechanical 9/21/2023 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 10/19/2023 Approved RYAN SALAZAR
PLUMBING-Rough 10/19/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 11/3/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Not Ready for Inspection RYAN SALAZAR
Shower Pan 11/3/2023 Approved RYAN SALAZAR
Wood Frame 11/3/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 11/7/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/7/2023 Approved RYAN SALAZAR
Green Building Rough 11/7/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 11/7/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/16/2023 Approved RYAN SALAZAR
Insulation 11/20/2023 Approved RYAN SALAZAR
Drywall Nailing 11/28/2023 Approved RYAN SALAZAR
Underground Mechanical 2/12/2024 Partial Approval RYAN SALAZAR
Underground Mechanical 2/16/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 4/10/2024 Partial Approval RYAN SALAZAR
HVAC-Final 4/10/2024 Approved RYAN SALAZAR
PLUMBING-Final 4/10/2024 Approved RYAN SALAZAR
Final 7/17/2024 Corrections Issued RYAN SALAZAR
Green Building Final 7/17/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 7/17/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 7/17/2024 Approved RYAN SALAZAR
Smoke Detectors 7/17/2024 Approved RYAN SALAZAR
Final 7/19/2024 OK to Issue CofO RYAN SALAZAR