613-613 1/2 W 41ST PL 90037

Certificate Information: 613-613 1/2 W 41ST PL 90037

Application / Permit
21010-10000-06754
Plan Check / Job No.
B21LA24109
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH ATTACHED CARPORT (REAR)
Permit Issued
Issued on 9/16/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 CARLOS MONTES
Corrections Issued 1/23/2022 ERIC WONG
Quality Review Completed 1/24/2022 PETER KIM
Applicant returned to address corrections 11/29/2022 ERIC WONG
Applicant returned to address corrections 12/19/2023 CARLOS MONTES
Applicant returned to address corrections 2/23/2024 CARLOS MONTES
Applicant returned to address corrections 3/4/2024 CARLOS MONTES
Applicant returned to address corrections 5/31/2024 CARLOS MONTES
Plan Check Approved 9/13/2024 CARLOS MONTES
Issued 9/16/2024 APPLICANT
CofO in Progress 11/13/2025 SABAS ALONSO
Permit Finaled 11/16/2025 DEROLD HAUFF
CofO Issued 11/16/2025 DEROLD HAUFF
Permit Finaled 11/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/27/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 2/1/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 3/3/2022 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 3/30/2022 JOHN CONNEALLY
Frnt yard landscape/Water mgmt Cleared 5/19/2022 DALIA MOKAYED
Permit Cleared 11/18/2022 CHRISTOPHER ROCHA
Low Impact Development Cleared 2/9/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 2/29/2024 WALLIE JONG
SB8 RUD Cleared 7/23/2024 BLAKE BOULIGNY

Contact Information

Contractor Owner-Builder       ,
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/12/2024 Approved CRAIG DAVIS
Underground Mechanical 11/12/2024 Approved CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 12/2/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 12/2/2024 Approved SABAS ALONSO
Deputy Reinf. Concrete 12/3/2024 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 12/26/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/2/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 2/24/2025 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Conditional Approval SABAS ALONSO
HVAC-Rough 2/25/2025 Approved SABAS ALONSO
Green Building Rough 2/27/2025 Not Ready for Inspection SABAS ALONSO
Shower Pan 3/13/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 3/14/2025 Approved SABAS ALONSO
Shower Pan 3/14/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 3/19/2025 Approved JOSE MACIAS
Interior/Exterior Lathing 3/19/2025 Approved JOSE MACIAS
BUILDING-Rough-Frame 3/21/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Approved SABAS ALONSO
Green Building Rough 3/21/2025 Approved SABAS ALONSO
Verify Sprinkler Sign Off 3/21/2025 Approved SABAS ALONSO
Insulation 4/2/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 4/2/2025 Approved ANTHONY RAMOS
Drywall Nailing 4/14/2025 Approved ANTHONY RAMOS
Underground Mechanical 6/6/2025 Approved JOSE MACIAS
Sewer 6/13/2025 Approved SABAS ALONSO
Underground Mechanical 6/13/2025 Approved SABAS ALONSO
ELECTRICAL-Final 9/17/2025 Not Ready for Inspection SABAS ALONSO
Final 9/17/2025 Corrections Issued SABAS ALONSO
HVAC-Final 9/17/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Final 9/17/2025 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 11/4/2025 Approved SABAS ALONSO
Gas Test 11/4/2025 Approved SABAS ALONSO
HVAC-Final 11/4/2025 Approved SABAS ALONSO
PLUMBING-Final 11/4/2025 Approved SABAS ALONSO
Final 11/6/2025 OK to Issue CofO SABAS ALONSO
Green Building Final 11/6/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/6/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 11/6/2025 Approved SABAS ALONSO
Smoke Detectors 11/6/2025 Approved SABAS ALONSO