613-613 1/2 W 41ST PL 90037
Certificate Information: 613-613 1/2 W 41ST PL 90037
- Application / Permit
- 21010-10000-06754
- Plan Check / Job No.
- B21LA24109
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX WITH ATTACHED CARPORT (REAR)
- Permit Issued
- Issued on 9/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | CARLOS MONTES |
| Corrections Issued | 1/23/2022 | ERIC WONG |
| Quality Review Completed | 1/24/2022 | PETER KIM |
| Applicant returned to address corrections | 11/29/2022 | ERIC WONG |
| Applicant returned to address corrections | 12/19/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 2/23/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 3/4/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 5/31/2024 | CARLOS MONTES |
| Plan Check Approved | 9/13/2024 | CARLOS MONTES |
| Issued | 9/16/2024 | APPLICANT |
| CofO in Progress | 11/13/2025 | SABAS ALONSO |
| Permit Finaled | 11/16/2025 | DEROLD HAUFF |
| CofO Issued | 11/16/2025 | DEROLD HAUFF |
| Permit Finaled | 11/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 3/3/2022 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 3/30/2022 | JOHN CONNEALLY |
| Frnt yard landscape/Water mgmt | Cleared | 5/19/2022 | DALIA MOKAYED |
| Permit | Cleared | 11/18/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 2/9/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/29/2024 | WALLIE JONG |
| SB8 RUD | Cleared | 7/23/2024 | BLAKE BOULIGNY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/12/2024 | Approved | CRAIG DAVIS |
| Underground Mechanical | 11/12/2024 | Approved | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 12/2/2024 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 12/2/2024 | Approved | SABAS ALONSO |
| Deputy Reinf. Concrete | 12/3/2024 | Conditional Approval | SABAS ALONSO |
| Deputy Steel/Welding | 12/26/2024 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 2/24/2025 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Conditional Approval | SABAS ALONSO |
| HVAC-Rough | 2/25/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 2/27/2025 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 3/13/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 3/14/2025 | Approved | SABAS ALONSO |
| Shower Pan | 3/14/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 3/19/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 3/19/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/21/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 3/21/2025 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 3/21/2025 | Approved | SABAS ALONSO |
| Insulation | 4/2/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 4/2/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 4/14/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 6/6/2025 | Approved | JOSE MACIAS |
| Sewer | 6/13/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/13/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 9/17/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 9/17/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 9/17/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 9/17/2025 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 11/4/2025 | Approved | SABAS ALONSO |
| Gas Test | 11/4/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 11/4/2025 | Approved | SABAS ALONSO |
| PLUMBING-Final | 11/4/2025 | Approved | SABAS ALONSO |
| Final | 11/6/2025 | OK to Issue CofO | SABAS ALONSO |
| Green Building Final | 11/6/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/6/2025 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 11/6/2025 | Approved | SABAS ALONSO |
| Smoke Detectors | 11/6/2025 | Approved | SABAS ALONSO |