1860-1860 1/2 W 24TH ST 90018
Certificate Information: 1860-1860 1/2 W 24TH ST 90018
- Application / Permit
- 21010-10000-06751
- Plan Check / Job No.
- B21LA24099
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 4-STORY DUPLEX BUILDING ATTACHED CARPORT (REAR LOT).
- Permit Issued
- Issued on 11/15/2023
- Issuing Office
- Metro
- Current Status
- Issued on 11/15/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/8/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/18/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| Applicant returned to address corrections | 8/15/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 6/23/2023 | MAHNAZ NOURHASHEMI |
| Issued | 11/15/2023 | APPLICANT |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 9/12/2022 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 9/19/2022 | WALTER RAMIREZ |
| Community Plan Implem. Overlay | Cleared | 9/21/2022 | ADALBERTO VERA |
| Address approval | Cleared | 9/26/2022 | STEVE MELGAR |
| Community Plan Implem. Overlay | Cleared | 9/26/2022 | STEVE MELGAR |
| Permit | Cleared | 9/26/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2022 | STEVE MELGAR |
| Building over 36-ft | Cleared | 11/1/2022 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 5/10/2023 | SARAH YOUSSEF |
| Community Plan Implem. Overlay | Cleared | 6/5/2023 | MOHAMMAD HASAN |
| Roof/Waste drainage to street | Cleared | 6/14/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 6/17/2023 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 6/21/2023 | LAVEON RIDER |
Contact Information
| Contractor | Sunny Construction & Development Corporation; Lic. No.: 737977-B | 711 S FIRST AVE ARCADIA, CA 91006 |
| Engineer | Lin,, Jason K; Lic. No.: S6095 | 1529 W LONGHILL DR MONTEREY PARK, CA 91754 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2024 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 9/24/2024 | Partial Approval | WILLIAM SIERRA |
| Deputy Reinf. Concrete | 10/2/2024 | Conditional Approval | WILLIAM SIERRA |
| Footing/Foundation/Slab | 10/2/2024 | Partial Approval | WILLIAM SIERRA |
| METHANE-Barrier | 10/2/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| METHANE-Subgrade | 10/2/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 10/9/2024 | Approved | WILLIAM SIERRA |
| METHANE-Barrier | 10/9/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| METHANE-Subgrade | 10/9/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Deputy Reinf. Concrete | 10/16/2024 | Conditional Approval | JOHN QUINTANILLA |
| Deputy Methane Barrier | 10/22/2024 | Conditional Approval | WILLIAM SIERRA |
| Footing/Foundation/Slab | 10/30/2024 | Approved | JOHN QUINTANILLA |
| METHANE-Barrier | 10/30/2024 | Approved | JOHN QUINTANILLA |
| METHANE-Subgrade | 10/30/2024 | Approved | JOHN QUINTANILLA |
| Sewer | 11/6/2024 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Approved | JOHN QUINTANILLA |
| Deputy Wood Construction | 12/12/2024 | Conditional Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Approved | JOHN QUINTANILLA |
| Deputy Wood Construction | 12/23/2024 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Approved | WILLIAM SIERRA |
| Green Building Rough | 1/23/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Rough | 4/14/2025 | Corrections Issued | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 4/15/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Green Building Rough | 4/15/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Rough | 4/15/2025 | Corrections Issued | WILLIAM SIERRA |
| MERV13>=Rough | 4/15/2025 | Approved | WILLIAM SIERRA |
| METHANE-Rough | 4/15/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 4/15/2025 | Approved | WILLIAM SIERRA |
| Verify Sprinkler Sign Off | 4/15/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Rough | 4/18/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 4/18/2025 | Conditional Approval | WILLIAM SIERRA |
| HVAC-Rough | 4/23/2025 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 4/25/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Rough | 4/25/2025 | Corrections Issued | WILLIAM SIERRA |
| Verify Sprinkler Sign Off | 4/25/2025 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 4/30/2025 | Approved | WILLIAM SIERRA |
| Green Building Rough | 4/30/2025 | Approved | WILLIAM SIERRA |
| Insulation | 5/7/2025 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 5/16/2025 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 5/19/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 6/13/2025 | Approved | WILLIAM SIERRA |
| Shower Pan | 6/13/2025 | Approved | WILLIAM SIERRA |
| Sewer | 7/21/2025 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 7/30/2025 | Partial Approval | LUIS CASTRO |
| Underground Mechanical | 8/7/2025 | Partial Approval | ANTHONY RAMOS |
| Underground Mechanical | 8/13/2025 | Partial Approval | JUSTIN HAWLEY |
| ELECTRICAL-Final | 1/12/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Final | 2/5/2026 | Approved | WILLIAM SIERRA |
| Service/Power Release | 4/16/2026 | Not Required | WILLIAM SIERRA |