4620 N YOSEMITE WAY 90041
Certificate Information: 4620 N YOSEMITE WAY 90041
- Application / Permit
- 21010-10000-06714
- Plan Check / Job No.
- B21LA24031
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 7/20/2022
- Issuing Office
- Current Status
- CofO Issued on 10/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | DANIEL YIP |
| Corrections Issued | 2/7/2022 | DANIEL YIP |
| Quality Review Completed | 2/7/2022 | LIPING TENG |
| Plan Check Approved | 7/8/2022 | DANIEL YIP |
| Issued | 7/20/2022 | APPLICANT |
| CofO in Progress | 9/27/2023 | CRAIG VAUGHAN |
| CofO Issued | 10/4/2023 | DEROLD HAUFF |
| Permit Finaled | 10/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/23/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 3/3/2022 | JEANETTE VONG |
| Address approval | Cleared | 3/15/2022 | JEANETTE VONG |
| Street Frontage | Cleared | 3/15/2022 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 5/19/2022 | RUEL COLE |
| Grading Pre-Inspection | Cleared | 7/8/2022 | DANIEL YIP |
Contact Information
| Architect | Vilppu,, Lydia Nadine; Lic. No.: C31349 | 3108 GLENDALE BLVD #512 LOS ANGELES, CA 90039 |
| Contractor | Urquia Marvin; Lic. No.: 1064984-B | 11146 VAN BUREN AVE LOS ANGELES, CA 90044 |
| Engineer | Alferez,, Vicente Narvaez; Lic. No.: C53875 | 460 E CARSON PLAZA DR STE 212 CARSON, CA 90746 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/3/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 11/3/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 11/10/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 11/14/2022 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 11/16/2022 | Approved | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 11/16/2022 | Approved | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 11/18/2022 | Conditional Approval | CRAIG VAUGHAN |
| Deputy Steel/Welding | 12/19/2022 | Conditional Approval | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 4/12/2023 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/12/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 4/12/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/12/2023 | Corrections Issued | CRAIG VAUGHAN |
| Shower Pan | 4/12/2023 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 4/12/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/19/2023 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2023 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/19/2023 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/25/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/25/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 4/25/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/25/2023 | Approved | CRAIG VAUGHAN |
| Sewer | 4/25/2023 | Corrections Issued | CRAIG VAUGHAN |
| Insulation | 5/2/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 5/2/2023 | Approved | CRAIG VAUGHAN |
| Sewer | 5/2/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 5/8/2023 | Approved | CRAIG VAUGHAN |
| Final | 8/8/2023 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 8/8/2023 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 8/8/2023 | Approved | CRAIG VAUGHAN |
| Final | 9/15/2023 | Corrections Issued | ROY SPAULDING |
| Final | 9/20/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 9/26/2023 | Approved | CRAIG VAUGHAN |
| Final | 9/26/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 9/26/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 9/26/2023 | Approved | CRAIG VAUGHAN |