360 1/2 N DETROIT ST 90036
Certificate Information: 360 1/2 N DETROIT ST 90036
- Application / Permit
- 21010-10000-06695
- Plan Check / Job No.
- B21LA23984
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU addition. 2ND STORY ADU ADDTION TO EXISTING GARAGE
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Current Status
- CofO Issued on 11/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 4/26/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 5/23/2022 | FARUK SEZER |
| Applicant returned to address corrections | 7/18/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 7/26/2022 | CRYSTEL MAALOUF |
| Issued | 7/27/2022 | APPLICANT |
| CofO in Progress | 8/23/2024 | JACOB MYERS |
| Permit Finaled | 11/22/2024 | ERNESTO CORRAL |
| CofO Issued | 11/22/2024 | ERNESTO CORRAL |
| Permit Finaled | 11/22/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 6/7/2022 | AMAAN MALIK |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD 230 TARZANA, CA 91356 |
| Engineer | Durand,, Paul H; Lic. No.: C58364 | 611 N G ST OXNARD, CA 93030 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/9/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Barrier | 3/9/2023 | Approved | JEROME BLACKWOOD |
| METHANE-Subgrade | 3/9/2023 | Approved | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 3/16/2023 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 3/28/2023 | Approved | ALFREDO LOPEZ |
| Green Building Rough | 5/3/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Rough | 5/3/2023 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 5/3/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 8/9/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| METHANE-Rough | 8/9/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 8/9/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 8/18/2023 | Approved | RONALD JIMENEZ |
| METHANE-Rough | 8/18/2023 | Approved | RONALD JIMENEZ |
| Wood Frame | 8/18/2023 | Approved | RONALD JIMENEZ |
| Insulation | 8/21/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Insulation | 8/22/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Insulation | 8/23/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 8/25/2023 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 8/29/2023 | Partial Approval | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 8/31/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 9/5/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 9/7/2023 | Partial Approval | JEROME BLACKWOOD |
| Final | 6/18/2024 | Conditional Approval | JACOB MYERS |
| Green Building Final | 6/18/2024 | Approved | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Approved | JACOB MYERS |
| Smoke Detectors | 6/18/2024 | Approved | JACOB MYERS |
| Final | 7/25/2024 | OK to Issue CofO | JACOB MYERS |