3417 W BELLEVUE AVE 90026
Certificate Information: 3417 W BELLEVUE AVE 90026
- Application / Permit
- 21010-10000-06683
- Plan Check / Job No.
- B21LA23944
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SFD AND 2-STORY ADU AT REAR OF LOT adu checked per lamc 12.22 a.33(c) and (e) 3 OF 3
- Permit Issued
- Issued on 5/16/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | SUNMIN LEE |
| Corrections Issued | 1/26/2022 | SUNMIN LEE |
| Quality Review Completed | 2/4/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 2/9/2022 | APPLICANT |
| Applicant returned to address corrections | 12/14/2022 | SUNMIN LEE |
| Plan Check Approved | 12/21/2022 | SUNMIN LEE |
| Issued | 5/16/2023 | APPLICANT |
| CofO in Progress | 7/28/2025 | FREDDIE RIVERA |
| Permit Finaled | 7/29/2025 | DEROLD HAUFF |
| CofO Issued | 7/29/2025 | DEROLD HAUFF |
| Permit Finaled | 7/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/30/2022 | STEVE MELGAR |
| Frnt yard landscape/Water mgmt | Cleared | 3/30/2022 | KENTON TRINH |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 4/21/2022 | STEVE MELGAR |
| Miscellaneous | Cleared | 6/15/2022 | ALBERT TAM |
| Highway dedication | Cleared | 6/30/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 7/7/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 11/20/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/26/2022 | STEVE MELGAR |
| GPI Written Notices | Cleared | 12/13/2022 | SUNMIN LEE |
| Grading Pre-Inspection | Cleared | 12/13/2022 | SUNMIN LEE |
Contact Information
| Contractor | Truebuilt Construction Inc; Lic. No.: 1052087-B | 950 E KATELLA AVE STE 5 ORANGE, CA 92867 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
| Engineer | Sunna,, Nadim; Lic. No.: GE3172 | 27035 MARISCAL LN MISSION VIEJO, CA 92691 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/11/2023 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 7/17/2023 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/21/2023 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 7/21/2023 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 7/21/2023 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 8/9/2023 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 11/27/2023 | Corrections Issued | FREDDIE RIVERA |
| Underground Mechanical | 12/15/2023 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 12/18/2023 | Partial Inspection | FREDDIE RIVERA |
| Sewer | 12/20/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 12/20/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 12/29/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 3/22/2024 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 3/22/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/3/2024 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/3/2024 | Partial Approval | FREDDIE RIVERA |
| MERV13>=Rough | 4/3/2024 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 4/3/2024 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 4/3/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/16/2024 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 4/16/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/16/2024 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/19/2024 | Conditional Approval | FREDDIE RIVERA |
| Insulation | 5/7/2024 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/9/2024 | Approved | FREDDIE RIVERA |
| Insulation | 5/9/2024 | Partial Approval | FREDDIE RIVERA |
| Insulation | 5/16/2024 | Conditional Approval | FREDDIE RIVERA |
| Drywall Nailing | 5/30/2024 | Approved | FREDDIE RIVERA |
| Shower Pan | 6/25/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 7/9/2024 | Approved | FREDDIE RIVERA |
| HVAC-Final | 1/21/2025 | Partial Approval | FREDDIE RIVERA |
| HVAC-Final | 3/12/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/1/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/18/2025 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 4/18/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 6/16/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/16/2025 | Approved | FREDDIE RIVERA |
| Green Building Final | 6/16/2025 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 6/16/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/16/2025 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 6/16/2025 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 6/16/2025 | Approved | FREDDIE RIVERA |
| Service/Power Release | 7/1/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 7/9/2025 | OK to Issue CofO | FREDDIE RIVERA |
| Service/Power Release | 7/9/2025 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 7/18/2025 | Approved | FREDDIE RIVERA |