16100 W MULHOLLAND DR 90049
Certificate Information: 16100 W MULHOLLAND DR 90049
- Application / Permit
- 21010-10000-06674
- Plan Check / Job No.
- B21LA23939
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (18) School Building
- Work Description
- (N) PRIVATE SCHOOL CLASSROOM BUILDING OF 16,130 SQFT AND STORAGE/TRASH BUILDING OF 1370 SQ FT. ASSOCAITED SITE WORK
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2021 | APPLICANT |
| Green Plans Picked Up | 1/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | HERNAN ARREOLA |
| Corrections Issued | 1/20/2022 | HERNAN ARREOLA |
| Disabled Access Plans Picked Up | 1/24/2022 | APPLICANT |
| Quality Review Completed | 1/25/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/26/2022 | APPLICANT |
| Applicant returned to address corrections | 3/7/2022 | HERNAN ARREOLA |
| Plan Check Approved | 6/21/2022 | HERNAN ARREOLA |
| Issued | 6/21/2022 | APPLICANT |
| TCO Issued (Expire Date: 02-24-2024) | 8/28/2023 | HENRY BAGHDASSARIAN |
| TCO Issued (Expire Date: 08-20-2024) | 2/22/2024 | HENRY BAGHDASSARIAN |
| TCO Issued (Expire Date: 02-15-2025) | 8/19/2024 | DAVID TSAU |
| CofO in Progress | 1/3/2025 | GRANT WOODS |
| Permit Finaled | 2/11/2025 | DAVID TSAU |
| CofO Issued | 2/11/2025 | DAVID TSAU |
| Permit Finaled | 2/11/2025 | DAVID TSAU |
Permit Application Clearance Information
| Highway dedication | Cleared | 2/22/2022 | HISASHI KOBAYAKAWA |
| Green Code | Cleared | 3/8/2022 | AARON COSTA |
| Address approval | Cleared | 4/5/2022 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 4/11/2022 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 4/21/2022 | KURT CORRAL |
| CPC | Cleared | 5/6/2022 | JASON CHAN |
| ZA Case | Cleared | 5/6/2022 | JASON CHAN |
| Fire Marshal Fire Life Safety | Cleared | 5/17/2022 | WILLIAM JOHNS |
| Internal circulation | Cleared | 5/24/2022 | FREDDY GARCIA |
| Trees in Parkway | Cleared | 5/30/2022 | ADALBERTO VERA |
| DAS Clearance | Cleared | 6/8/2022 | CHOI YAN |
| Low Impact Development | Cleared | 6/13/2022 | MARTIN FRAGOSO |
| CPC | Cleared | 6/15/2022 | JASON CHAN |
| Roof/Waste drainage to street | Cleared | 6/15/2022 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 6/15/2022 | JASON CHAN |
| GPI Written Notices | Cleared | 6/21/2022 | HERNAN ARREOLA |
| Grading Pre-Inspection | Cleared | 6/21/2022 | HERNAN ARREOLA |
Contact Information
| Architect | Johnson,, Steven Long; Lic. No.: C17181 | 5898 BLACKWELDER STREET CULVER CITY, CA 90232 |
| Contractor | Del Amo Construction Inc; Lic. No.: 744458-B | 23840 MADISON STREET TORRANCE, CA 90505 |
| Engineer | Kocijan,, Jerko; Lic. No.: GE2969 | 924 ANACAPA STREET, SUITE 4A SANTA BARBARA, CA 93101 |
| Engineer | Powers,, Brian Frederick; Lic. No.: C75902 | 5712 S. VICTORIA AVE LOS ANGELES, CA 90043 |
| Engineer | Sabol,, Thomas Andrew; Lic. No.: S3175 | 888 S FIGUEROA ST 18TH FL LOS ANGELES, CA 90017 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 6/24/2022 | Partial Approval | DERRICK SPENCER |
| Deputy Methane Barrier | 7/15/2022 | Approved | DERRICK SPENCER |
| Deputy Methane Barrier | 7/18/2022 | Approved | DERRICK SPENCER |
| Deputy Methane Barrier | 7/19/2022 | Approved | DERRICK SPENCER |
| Pre-Inspection | 7/21/2022 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 7/26/2022 | Partial Approval | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 7/26/2022 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 8/2/2022 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/2/2022 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/9/2022 | Approved | DERRICK SPENCER |
| Masonry Wall/Backfill | 8/22/2022 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 10/7/2022 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/12/2022 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | No Access for Inspection | GRANT WOODS |
| Wall Anchors | 12/22/2022 | No Access for Inspection | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 1/19/2023 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 1/19/2023 | Approved | DERRICK SPENCER |
| Light Gage Steel Frame | 1/19/2023 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 1/19/2023 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 1/23/2023 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 1/23/2023 | Partial Approval | DERRICK SPENCER |
| Wall Anchors | 1/23/2023 | Approved | DERRICK SPENCER |
| Drywall Nailing | 2/16/2023 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 2/27/2023 | Partial Approval | DERRICK SPENCER |
| Insulation | 2/27/2023 | Partial Approval | DERRICK SPENCER |
| SWPPP-Const. Storm Water | 3/13/2023 | Completed | DERRICK SPENCER |
| Drywall Nailing | 4/5/2023 | Partial Approval | DERRICK SPENCER |
| Insulation | 4/5/2023 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 4/5/2023 | Partial Approval | DERRICK SPENCER |
| Insulation | 4/14/2023 | Partial Approval | DERRICK SPENCER |
| Interior/Exterior Lathing | 5/22/2023 | Partial Approval | DERRICK SPENCER |
| T-Bar Ceiling | 8/7/2023 | Approved | DERRICK SPENCER |
| Pre-Inspection | 8/16/2023 | Approved | DERRICK SPENCER |
| Pre-Inspection | 8/22/2023 | Approved | DERRICK SPENCER |
| Final | 8/23/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/23/2023 | Approved | DERRICK SPENCER |
| Green Building Final | 8/23/2023 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 8/23/2023 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 8/23/2023 | Approved | DERRICK SPENCER |
| Wood Frame | 8/23/2023 | Approved | DERRICK SPENCER |
| Deputy Methane Barrier | 9/18/2023 | Approved | DERRICK SPENCER |
| Deputy Methane Barrier | 9/18/2023 | Conditional Approval | DERRICK SPENCER |
| Final | 1/23/2024 | Corrections Issued | GRANT WOODS |
| Special/Order Compliance | 1/30/2024 | Approved | GRANT WOODS |
| Pre-Inspection | 2/29/2024 | Partial Approval | GRANT WOODS |
| Special/Order Compliance | 3/18/2024 | Approved | GRANT WOODS |
| Final | 5/15/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 5/30/2024 | Conditional Approval | GRANT WOODS |
| Special/Order Compliance | 7/23/2024 | Partial Approval | GRANT WOODS |
| Special/Order Compliance | 1/22/2025 | Partial Inspection | GRANT WOODS |