12515 W BARBARA AVE 90066

Certificate Information: 12515 W BARBARA AVE 90066

Application / Permit
21010-10000-06669
Plan Check / Job No.
B21LA23919
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 4/26/2022
Issuing Office
Current Status
CofO Issued on 6/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 DANIEL YIP
Corrections Issued 1/24/2022 DANIEL YIP
Quality Review Completed 1/24/2022 LIPING TENG
Plan Check Approved 4/22/2022 DANIEL YIP
Issued 4/26/2022 APPLICANT
CofO in Progress 6/15/2023 JESUS RODRIGUEZ
Permit Finaled 6/26/2023 DANIEL ORRANTE
CofO Issued 6/26/2023 DANIEL ORRANTE
Permit Finaled 6/26/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/26/2022 DINAH GARIN
Low Impact Development Cleared 3/23/2022 ANTHONY VARGAS
Eng Process Fee Ord 176,300 Cleared 4/12/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 4/12/2022 DINAH GARIN
Sewer availability Cleared 4/12/2022 DINAH GARIN
Construction near power lines Cleared 4/13/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: S6930 20182 MCKINLEY LN      HUNTINGTON BEACH, CA 92646
Engineer Zhang,, Zhiqiang; Lic. No.: M34617 410 S SAN GABRIEL BLVD #8      SAN GABRIEL, CA 91776

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/16/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Rough 5/16/2022 Corrections Issued PATRICK QUALEY
Footing/Foundation/Slab 6/6/2022 Corrections Issued PATRICK QUALEY
Sewer 6/28/2022 Approved PATRICK QUALEY
Excavation/Setback/Form/Re-Bar 6/30/2022 Approved PATRICK QUALEY
Sewer 6/30/2022 Approved PATRICK QUALEY
BUILDING-Rough-Frame 9/27/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 9/27/2022 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 9/27/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 9/27/2022 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 9/27/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 9/29/2022 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 9/29/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 9/29/2022 Approved JESUS RODRIGUEZ
Rough-Elec/Plmb/HVAC 9/29/2022 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/15/2022 Approved JESUS RODRIGUEZ
Sewer 11/15/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 11/15/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/5/2022 Approved JESUS RODRIGUEZ
Shower Pan 12/5/2022 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 12/8/2022 Approved JESUS RODRIGUEZ
Insulation 12/8/2022 Approved JESUS RODRIGUEZ
Shower Pan 12/8/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 12/13/2022 Approved RICHARD STEINBACH
BUILDING-Rough-Frame 3/23/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 3/23/2023 Corrections Issued JESUS RODRIGUEZ
Final 3/23/2023 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 3/23/2023 Approved JESUS RODRIGUEZ
HVAC-Final 3/23/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 3/23/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/23/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 3/23/2023 Corrections Issued JESUS RODRIGUEZ
Smoke Detectors 3/23/2023 Approved JESUS RODRIGUEZ
Final 4/17/2023 No Access for Inspection HERBERT GIRON
Service/Power Release 4/17/2023 No Access for Inspection HERBERT GIRON
Service/Power Release 4/18/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Final 5/5/2023 Corrections Issued JESUS RODRIGUEZ
Final 5/5/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 5/5/2023 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 5/5/2023 Not Ready for Inspection JESUS RODRIGUEZ
Final 5/11/2023 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 5/11/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 6/14/2023 Approved JESUS RODRIGUEZ
Final 6/14/2023 OK to Issue CofO JESUS RODRIGUEZ
Service/Power Release 6/14/2023 Approved JESUS RODRIGUEZ