944 1/2 N FLINT AVE 90744
Certificate Information: 944 1/2 N FLINT AVE 90744
- Application / Permit
- 21010-10000-06664
- Plan Check / Job No.
- B21LA23911
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan (E) Garage converted to ADU Per Ordinance 186481
- Permit Issued
- Issued on 3/30/2022
- Issuing Office
- Current Status
- CofO Issued on 3/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/24/2021 | HERNAN ARREOLA |
| Corrections Issued | 12/27/2021 | HERNAN ARREOLA |
| Plan Check Approved | 2/24/2022 | HERNAN ARREOLA |
| Issued | 3/30/2022 | APPLICANT |
| CofO in Progress | 3/16/2023 | EUGENE CASSIDY |
| CofO Issued | 3/21/2023 | ANSON MAGLASANG |
| Permit Finaled | 3/21/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/1/2022 | MAXFIELD VERMY |
| Address approval | Cleared | 2/2/2022 | HUGO LOPEZ |
| Sewer availability | Cleared | 2/2/2022 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | HUGO LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/8/2022 | Partial Approval | EUGENE CASSIDY |
| Gas Test | 4/8/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 4/8/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Sewer | 4/8/2022 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 4/8/2022 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/12/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/12/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/19/2022 | Approved | EUGENE CASSIDY |
| Green Building Rough | 5/19/2022 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 5/19/2022 | Approved | EUGENE CASSIDY |
| Insulation | 5/19/2022 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 5/19/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 6/1/2022 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Final | 1/13/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 1/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/13/2023 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 1/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 2/24/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/24/2023 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 2/24/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/16/2023 | Approved | EUGENE CASSIDY |
| Final | 3/16/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 3/16/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 3/16/2023 | Approved | EUGENE CASSIDY |