3438 S CARMONA AVE 90016

Certificate Information: 3438 S CARMONA AVE 90016

Application / Permit
21010-10000-06663
Plan Check / Job No.
B21LA23910
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED HCD approved and inspected Factory Built Housing ADU.
Permit Issued
Issued on 2/11/2022
Issuing Office
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2022 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 JOE VO
Corrections Issued 1/7/2022 JOE VO
Applicant returned to address corrections 1/27/2022 JOE VO
Plan Check Approved 2/9/2022 JOE VO
Issued 2/11/2022 APPLICANT
CofO in Progress 8/31/2023 JOSE AVILA
CofO Issued 9/25/2023 DEROLD HAUFF
Permit Finaled 9/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/3/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 2/3/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/7/2022 WALLIE JONG
Sewer availability Cleared 2/7/2022 WALLIE JONG

Contact Information

Contractor Abodu Inc; Lic. No.: 1073522-B       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/11/2022 Approved JOSE AVILA
PLUMBING-Rough 7/26/2022 Corrections Issued JOSE AVILA
Sewer 7/26/2022 Corrections Issued JOSE AVILA
Underground Mechanical 7/26/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 10/7/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 1/3/2023 Partial Approval JOSE AVILA
Sewer 1/3/2023 Corrections Issued JOSE AVILA
Sewer 1/6/2023 Partial Approval MARK BURTON
ELECTRICAL-Final 2/2/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 3/17/2023 Partial Inspection JOSE AVILA
Green Building Rough 3/17/2023 Approved JOSE AVILA
Verify Sprinkler Sign Off 3/17/2023 Partial Approval JOSE AVILA
Pre-Inspection 4/4/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 8/30/2023 Approved JOSE AVILA
Final 8/30/2023 OK to Issue CofO JOSE AVILA
Green Building Final 8/30/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/30/2023 SGSOV Approved JOSE AVILA
Service/Power Release 8/30/2023 Approved JOSE AVILA
Smoke Detectors 8/30/2023 Approved JOSE AVILA
Verify Sprinkler Sign Off 8/30/2023 Approved JOSE AVILA