3945 S TIVOLI AVE 90066
Certificate Information: 3945 S TIVOLI AVE 90066
- Application / Permit
- 21010-10000-06622
- Plan Check / Job No.
- B21LA23824
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU
- Permit Issued
- Issued on 9/1/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2022 | JOSEPH RAFOLS |
| Corrections Issued | 1/12/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| Applicant returned to address corrections | 6/9/2022 | MINA HABILI |
| Plan Check Approved | 7/18/2022 | DANIEL SANJUAN |
| Issued | 9/1/2022 | APPLICANT |
| CofO in Progress | 8/6/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/7/2024 | DANIEL ORRANTE |
| CofO Issued | 8/7/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/7/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/5/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 3/15/2022 | SAUL GARCIA |
| Specific Plan | Cleared | 3/21/2022 | FREDDY GARCIA |
| Construction near power lines | Cleared | 6/1/2022 | WALTER RAMIREZ |
| Address approval | Cleared | 7/18/2022 | CINDY QI |
Contact Information
| Contractor | F S Builders Group Inc; Lic. No.: 999313-B | 19016 ARCHWOOD ST UNIT 9 RESEDA, CA 91335 |
| Engineer | Ng,, Edward Tw; Lic. No.: C38552 | 979 E MUNCIE AVE FRESNO, CA 93720 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/16/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/16/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/6/2023 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/22/2023 | Approved | JESUS RODRIGUEZ |
| Final | 6/15/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Sewer | 6/15/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 6/15/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/27/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 7/27/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 7/27/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 8/24/2023 | Approved | JESUS RODRIGUEZ |
| Rough-Elec/Plmb/HVAC | 8/24/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/29/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/1/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 9/1/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 9/1/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 9/13/2023 | Partial Approval | TEMISTOCLES CAAL |
| Drywall Nailing | 10/4/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 10/4/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/17/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/14/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 6/14/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 6/14/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 6/14/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/14/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 6/14/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/2/2024 | Approved | JESUS RODRIGUEZ |
| Final | 8/2/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| HVAC-Final | 8/2/2024 | Approved | JESUS RODRIGUEZ |