4186 S WESTERN AVE 1-118 90062

Certificate Information: 4186 S WESTERN AVE 1-118 90062

Application / Permit
21010-10000-06572
Plan Check / Job No.
B21LA23760
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePLAN. NEW 7 STORY 118 UNIT 100% AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 2 STORY TYPE IA APARTMENT, AB 1763/AB2345/12.22.A25 WITH ADDITIONAL INCENTIVES
Permit Issued
Issued on 5/30/2024
Issuing Office
Metro
Current Status
Issued on 5/30/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/21/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 KEVIN MORALES
Corrections Issued 1/20/2022 KEVIN MORALES
Quality Review Completed 1/25/2022 EUGENE BARBEAU
Applicant returned to address corrections 3/16/2022 KEVIN MORALES
Applicant returned to address corrections 5/3/2022 KEVIN MORALES
Applicant returned to address corrections 6/14/2022 KEVIN MORALES
Applicant returned to address corrections 8/9/2022 KEVIN MORALES
Applicant returned to address corrections 9/29/2022 KEVIN MORALES
Applicant returned to address corrections 10/19/2022 KEVIN MORALES
Applicant returned to address corrections 12/1/2022 KEVIN MORALES
Plan Check Approved 5/1/2024 KEVIN MORALES
Plan Check Approved 5/29/2024 KEVIN MORALES
Issued 5/30/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/28/2022 JEANIE LAM
Community Plan Implem. Overlay Cleared 1/28/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/28/2022 JEANIE LAM
Miscellaneous Cleared 3/8/2023 SPENCER WEJROWSKI
Miscellaneous Cleared 3/8/2023 SPENCER WEJROWSKI
Hydrant and Access approval Cleared 6/5/2023 KURT CORRAL
Highway dedication Cleared 7/27/2023 ADRIAN SANCHEZ
Encroachment in public way Cleared 8/4/2023 KATHERINE MENDOZA
DAS Clearance Cleared 8/7/2023 KEVIN MORALES
Community Plan Implem. Overlay Cleared 8/31/2023 COLLINS ALLAN
Community Plan Implem. Overlay Cleared 9/7/2023 ADALBERTO VERA
Trees in Parkway Cleared 9/8/2023 ADALBERTO VERA
Community Plan Implem. Overlay Cleared 9/20/2023 RAFAEL FONTES
Miscellaneous Cleared 9/20/2023 RAFAEL FONTES
Community Plan Implem. Overlay Cleared 11/14/2023 RIDWAN HARDY
Green Code Cleared 12/7/2023 KEVIN MORALES
Miscellaneous Cleared 12/18/2023 DAVID URITA
Opn space landscape/Water mgmt Cleared 12/18/2023 DAVID URITA
Fire Marshal Fire Life Safety Cleared 12/28/2023 MENOA AGHAJANI
Building over 36-ft Cleared 1/9/2024 CALOSHA APPROVED
Low Impact Development Cleared 4/12/2024 SARAH YOUSSEF
Sewer availability Cleared 4/17/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 4/18/2024 TREVOR QUAN
Permit Cleared 4/19/2024 CELINA MORENO
Density Bonus 12.22.A.31 Cleared 5/29/2024 ALYSSA FLORES

Contact Information

Architect Kil,, Andrew Han; Lic. No.: C31817 13005 MESA VERDE WAY      SYLMAR, CA 91342
Contractor ; Lic. No.: 1017728-B       ,
Engineer Lee,, Allen; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670
Engineer Lee,, Sang Youck; Lic. No.: NA3821       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/18/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/27/2024 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/27/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/16/2024 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 8/16/2024 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Rough 8/16/2024 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 8/16/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/16/2024 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/19/2024 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 8/19/2024 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/20/2024 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 8/20/2024 Partial Approval RAFAEL ESPINOZA
Green Building Rough 9/3/2024 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 9/3/2024 Partial Inspection LARRY ARNICK
Reinforced Concrete Frame 9/3/2024 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 9/3/2024 Not Ready for Inspection LARRY ARNICK
Structural Steel Frame 9/6/2024 Partial Inspection DARRYL ARNOLD
Deputy Drilled-In Anchors 9/17/2024 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/17/2024 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 9/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 9/17/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 9/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/8/2024 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 10/8/2024 Partial Inspection RAFAEL ESPINOZA
Green Building Rough 10/11/2024 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 10/11/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/11/2024 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Drilled-In Anchors 10/23/2024 Conditional Approval RAFAEL CORTES
Deputy Reinf. Concrete 10/23/2024 Conditional Approval RAFAEL CORTES
Structural Steel Frame 10/23/2024 Partial Inspection RAFAEL CORTES
Deputy Reinf. Concrete 10/25/2024 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 10/25/2024 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 10/25/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/25/2024 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Drilled-In Anchors 10/29/2024 Conditional Approval RAFAEL CORTES
Deputy Reinf. Concrete 10/29/2024 Conditional Approval RAFAEL CORTES
Structural Steel Frame 10/29/2024 Partial Approval RAFAEL CORTES
Reinforced Concrete Frame 11/22/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/27/2024 Conditional Approval RAFAEL CORTES
Reinforced Concrete Frame 11/27/2024 Partial Approval RAFAEL CORTES
Wood Frame 1/7/2025 Partial Approval RAFAEL CORTES
Wood Frame 1/13/2025 Partial Approval RAFAEL CORTES
Deputy Wood Construction 1/27/2025 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/11/2025 Conditional Approval RAFAEL CORTES
Wood Frame 2/11/2025 Partial Approval RAFAEL CORTES
Wood Frame 2/18/2025 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/24/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 4/2/2025 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Partial Approval RAFAEL ESPINOZA
Wood Frame 4/10/2025 No Access for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 4/11/2025 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/22/2025 Conditional Approval RAFAEL CORTES
Wood Frame 4/22/2025 Partial Approval RAFAEL CORTES
Deputy Reinf. Concrete 5/2/2025 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 5/2/2025 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 5/5/2025 Partial Approval JAMES POWERS
Insulation 5/8/2025 Not Ready for Inspection RAFAEL CORTES
Interior/Exterior Lathing 5/9/2025 Partial Approval RAFAEL CORTES
Wood Frame 5/9/2025 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 5/13/2025 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 5/13/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/14/2025 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/16/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/23/2025 Partial Approval RAFAEL ESPINOZA
Insulation 5/23/2025 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/23/2025 Partial Approval RAFAEL ESPINOZA