10957-10959 W CALVERT ST 91606
Certificate Information: 10957-10959 W CALVERT ST 91606
- Application / Permit
- 21010-10000-06562
- Plan Check / Job No.
- B21LA23725
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX WITH RECREATION ROOM (BLDG A)
- Permit Issued
- Issued on 10/2/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2021 | STARR CHEN |
| Corrections Issued | 1/2/2022 | STARR CHEN |
| Quality Review Completed | 1/6/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| Applicant returned to address corrections | 10/31/2022 | STARR CHEN |
| Plan Check Approved | 1/11/2023 | STARR CHEN |
| Issued | 10/2/2023 | APPLICANT |
| CofO in Progress | 8/18/2025 | JOSE AVILA |
| Permit Finaled | 8/20/2025 | RUBEN SALAS |
| CofO Issued | 8/20/2025 | RUBEN SALAS |
| Permit Finaled | 8/20/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 2/2/2022 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 2/2/2022 | NOAH MCCOY |
| Tract Map conditions | Cleared | 2/2/2022 | LOUIS ORTEGA |
| Address approval | Cleared | 4/15/2022 | DAGOVERTO GUERRERO |
| Permit | Cleared | 4/15/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/18/2022 | DAGOVERTO GUERRERO |
| Trees in Parkway | Cleared | 5/13/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 9/9/2022 | JOHN CONNEALLY |
| Frnt yard landscape/Water mgmt | Cleared | 11/21/2022 | LOUIS ORTEGA |
| Opn space landscape/Water mgmt | Cleared | 11/21/2022 | LOUIS ORTEGA |
| Low Impact Development | Cleared | 12/16/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 12/20/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Desai,, Anil T; Lic. No.: C24653 | 1530 VIA LOS COYOTES LA HABRA, CA 90631 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/5/2023 | No Access for Inspection | JOHN HAYES |
| Deputy Reinf. Concrete | 3/27/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 4/2/2024 | Not Ready for Inspection | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/8/2024 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 4/8/2024 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 4/26/2024 | Corrections Issued | JACK KARGODORIAN |
| Underground Mechanical | 5/1/2024 | Approved | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 5/6/2024 | Approved | JOHN HAYES |
| Deputy Steel/Welding | 5/16/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2024 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 7/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/16/2024 | Partial Approval | JOSE AVILA |
| Shower Pan | 9/4/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 9/16/2024 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 9/19/2024 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 9/26/2024 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 9/26/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 10/8/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 10/8/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 10/8/2024 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 10/8/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 10/17/2024 | Approved | JOSE AVILA |
| Insulation | 10/17/2024 | Approved | JOSE AVILA |
| Special/Order Compliance | 10/17/2024 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 10/28/2024 | Approved | MICHAEL CORTEZ |
| PLUMBING-Rough | 12/19/2024 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 1/22/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 1/28/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 1/29/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 2/14/2025 | Approved | JOSE AVILA |
| PLUMBING-Final | 4/10/2025 | Approved | JOSE AVILA |
| Service/Power Release | 4/10/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 4/11/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 4/14/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 6/2/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 6/2/2025 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Final | 6/12/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 6/23/2025 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Final | 6/27/2025 | Approved | JOSE AVILA |
| Special/Order Compliance | 7/31/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 8/1/2025 | Partial Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | JOSE AVILA |
| Final | 8/15/2025 | OK to Issue CofO | JOSE AVILA |
| Footing/Foundation/Slab | 8/15/2025 | Approved | JOSE AVILA |
| Green Building Final | 8/15/2025 | Approved | JOSE AVILA |
| Green Building Rough | 8/15/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 8/15/2025 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 8/15/2025 | Approved | JOSE AVILA |
| Smoke Detectors | 8/15/2025 | Approved | JOSE AVILA |
| Structural Steel Frame | 8/15/2025 | Approved | JOSE AVILA |