164 S BARLOCK AVE 90049
Certificate Information: 164 S BARLOCK AVE 90049
- Application / Permit
- 21010-10000-06560
- Plan Check / Job No.
- B21LA23715
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU WITH ATTACHED PERGOLA AND BASEMENT STORAGE. PER ORDINANCE
- Permit Issued
- Issued on 10/19/2022
- Issuing Office
- Current Status
- Issued on 10/19/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | MONICA RAMIREZ |
| Corrections Issued | 1/4/2022 | MONICA RAMIREZ |
| Quality Review Completed | 1/5/2022 | MICHAEL PEREZ |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| Applicant returned to address corrections | 9/2/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 9/16/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 9/26/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 10/17/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 10/19/2022 | CRYSTEL MAALOUF |
| Issued | 10/19/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/15/2022 | JOSE RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2022 | JOSE RODRIGUEZ |
| Hydrant and Access approval | Cleared | 6/10/2022 | LAVEON RIDER |
| Permit | Cleared | 8/16/2022 | JENSON LEE |
| Sewer availability | Cleared | 8/16/2022 | JENSON LEE |
| Street Frontage | Cleared | 8/16/2022 | JENSON LEE |
| Specific Plan | Cleared | 8/18/2022 | FREDDY GARCIA |
| Trees in Parkway | Cleared | 9/2/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 9/7/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/8/2022 | CATHERINE ADROVER |
| Miscellaneous | Cleared | 9/15/2022 | SAUL GARCIA |
| GPI Written Notices | Cleared | 9/16/2022 | MONICA RAMIREZ |
| Grading Pre-Inspection | Cleared | 9/16/2022 | MONICA RAMIREZ |
| Miscellaneous | Cleared | 9/16/2022 | MONICA RAMIREZ |
Contact Information
| Architect | Adams,, Lauren Amanda; Lic. No.: C30146 | 8695 WASHINGTON BLVD SUITE 205 CULVER CITY, CA 90232 |
| Contractor | Letter Four Inc; Lic. No.: 1028949-B | 12822 WASHINGTN BLVD LOS ANGELES, CA 90066 |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 21126 MERRIDY STREET CHATSWORTH, CA 91311 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Corrections Issued | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 2/21/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 2/22/2023 | Partial Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 4/6/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 4/17/2023 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 5/17/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 5/24/2023 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/12/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 6/15/2023 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 6/21/2023 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/23/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 10/27/2023 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 10/27/2023 | Approved | CARLOS MATAMOROS |
| Gas Test | 10/30/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/30/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 12/7/2023 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 12/7/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Special/Order Compliance | 12/7/2023 | Corrections Issued | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 12/13/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Shower Pan | 12/13/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Shower Pan | 12/18/2023 | Approved | CHRISTOPHER WILSON |
| Insulation | 12/20/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/5/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 1/5/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/5/2024 | Partial Approval | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 1/5/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/8/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/10/2024 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 1/16/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 1/16/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 5/20/2024 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 5/21/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 5/23/2024 | Approved | CARLOS MATAMOROS |
| Gas Test | 6/13/2024 | Approved | CARLOS MATAMOROS |
| Green Building Final | 6/13/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 6/13/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 6/13/2024 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 6/13/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 7/22/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 7/22/2024 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/6/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Service/Power Release | 9/6/2024 | Approved | CARLOS MATAMOROS |