516 W 105TH ST 90044

Certificate Information: 516 W 105TH ST 90044

Application / Permit
21010-10000-06553
Plan Check / Job No.
B21LA23681
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW DETACHED (23' X 31.5') ADU (ZC: 661 SF) PER CA GC 65852.2(e)(1)(B) AND LAMC 12.22.A.33(c)-(d), (g).
Permit Issued
Issued on 9/20/2022
Issuing Office
Current Status
Issued on 9/20/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/24/2022 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 VIVIAN LAO
Corrections Issued 2/5/2022 VIVIAN LAO
Quality Review Completed 2/7/2022 LIPING TENG
Applicant returned to address corrections 3/24/2022 VIVIAN LAO
Plan Check Approved 9/20/2022 VIVIAN LAO
Issued 9/20/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/15/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/23/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 3/23/2022 WALLIE JONG
Sewer availability Cleared 3/23/2022 WALLIE JONG
Construction near power lines Cleared 4/23/2022 RIDWAN HARDY
Low Impact Development Cleared 7/8/2022 ANTHONY VARGAS

Contact Information

Contractor L A Developing Inc; Lic. No.: 1083426-B       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/19/2022 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 10/28/2022 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 11/14/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 12/21/2022 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Approved JAMES CHAVEZ
PLUMBING-Rough 12/21/2022 Approved JAMES CHAVEZ
HVAC-Rough 12/30/2022 Approved JAMES CHAVEZ
Interior/Exterior Lathing 12/30/2022 Approved JAMES CHAVEZ
Insulation 1/3/2023 Approved JAMES CHAVEZ
Drywall Nailing 1/11/2023 Approved JAMES CHAVEZ
Green Building Rough 1/11/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 1/11/2023 Approved JAMES CHAVEZ
ELECTRICAL-Final 2/2/2023 Approved JAMES CHAVEZ
PLUMBING-Final 2/2/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 4/18/2023 Approved JAMES CHAVEZ
Final 4/18/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 4/18/2023 Corrections Issued JAMES CHAVEZ
MERV13>=Final 4/18/2023 Approved JAMES CHAVEZ
MERV13>=Rough 4/18/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Approved JAMES CHAVEZ
Service/Power Release 4/18/2023 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 4/18/2023 Approved JAMES CHAVEZ
Verify Sprinkler Sign Off 4/18/2023 Approved JAMES CHAVEZ
Final 6/7/2023 No Access for Inspection JAMES CHAVEZ
Green Building Final 6/7/2023 No Access for Inspection JAMES CHAVEZ
Service/Power Release 6/7/2023 No Access for Inspection JAMES CHAVEZ
Final 7/17/2023 No Access for Inspection JAMES CHAVEZ
Green Building Final 7/17/2023 No Access for Inspection JAMES CHAVEZ
Service/Power Release 7/17/2023 No Access for Inspection JAMES CHAVEZ
Final 8/17/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Final 8/17/2023 Not Ready for Inspection JAMES CHAVEZ
Service/Power Release 8/17/2023 Not Ready for Inspection JAMES CHAVEZ
Final 7/28/2025 Corrections Issued BEN MOLSTAD
Green Building Final 7/28/2025 Corrections Issued BEN MOLSTAD
Service/Power Release 7/28/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 8/7/2025 Corrections Issued BEN MOLSTAD
Final 8/7/2025 Corrections Issued BEN MOLSTAD
Green Building Final 8/7/2025 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 8/7/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Final 8/7/2025 Corrections Issued BEN MOLSTAD
Service/Power Release 8/7/2025 Not Ready for Inspection BEN MOLSTAD
Final 10/24/2025 Corrections Issued ANTHONY EGSON
Green Building Final 10/24/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 11/5/2025 Corrections Issued BEN MOLSTAD
Final 11/5/2025 Corrections Issued BEN MOLSTAD
Green Building Final 11/5/2025 Not Ready for Inspection BEN MOLSTAD
Service/Power Release 11/5/2025 Not Ready for Inspection BEN MOLSTAD