2321 E FERNLEAF ST 90031

Certificate Information: 2321 E FERNLEAF ST 90031

Application / Permit
21010-10000-06552
Plan Check / Job No.
B21LA20576
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1 STORY ADU PER STATE LAW
Permit Issued
Issued on 6/20/2023
Issuing Office
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 JAD BASMA
Corrections Issued 12/20/2021 JAD BASMA
Quality Review Completed 12/23/2021 MICHAEL PEREZ
Building Plans Picked Up 12/28/2021 APPLICANT
Applicant returned to address corrections 6/22/2022 JAD BASMA
Applicant returned to address corrections 10/18/2022 JAD BASMA
Applicant returned to address corrections 11/1/2022 JAD BASMA
Plan Check Approved 11/7/2022 JAD BASMA
Plan Check Approved 6/20/2023 JAD BASMA
Issued 6/20/2023 APPLICANT
CofO in Progress 5/23/2024 HAMIK HARTOUNIAN
CofO Issued 5/29/2024 DEROLD HAUFF
Permit Finaled 5/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/25/2022 STEVE MELGAR
Green Code Cleared 10/18/2022 JAD BASMA
Eng Process Fee Ord 176,300 Cleared 5/25/2023 TREVOR QUAN
Sewer availability Cleared 5/25/2023 TREVOR QUAN
Low Impact Development Cleared 6/12/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/13/2023 WALLIE JONG
Construction near power lines Cleared 6/20/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/27/2023 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 8/7/2023 Corrections Issued THOMAS LOGRASSO
Deputy Reinf. Concrete 8/8/2023 Conditional Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 8/16/2023 Approved THOMAS LOGRASSO
Deputy Reinf. Concrete 8/17/2023 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Partial Approval THOMAS LOGRASSO
Sewer 10/10/2023 Not Ready for Inspection CHARLES BOGHOSKHAN
Sewer 10/12/2023 Approved CHARLES BOGHOSKHAN
Deputy Wood Construction 11/1/2023 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Partial Approval THOMAS LOGRASSO
MERV13>=Rough 11/1/2023 Approved THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 11/1/2023 Corrections Issued THOMAS LOGRASSO
Verify Sprinkler Sign Off 11/1/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 11/13/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 11/13/2023 Partial Approval THOMAS LOGRASSO
Insulation 11/16/2023 Corrections Issued KATHRYN BUTTERWORTH
Drywall Nailing 11/28/2023 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 11/28/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 12/4/2023 Approved THOMAS LOGRASSO
Final 3/29/2024 Not Ready for Inspection THOMAS LOGRASSO
Gas Test 4/1/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 4/12/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 4/17/2024 Corrections Issued THOMAS LOGRASSO
Gas Test 4/18/2024 Not Ready for Inspection JOSEPH MCGARRY
Final 4/22/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 5/8/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 5/8/2024 Approved HAMIK HARTOUNIAN
Final 5/8/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/8/2024 Approved HAMIK HARTOUNIAN
Green Building Final 5/8/2024 Approved HAMIK HARTOUNIAN
Green Building Rough 5/8/2024 Approved HAMIK HARTOUNIAN
HVAC-Final 5/8/2024 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 5/8/2024 Approved HAMIK HARTOUNIAN
PLUMBING-Final 5/8/2024 Approved HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 5/8/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/8/2024 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 5/8/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 5/8/2024 Approved HAMIK HARTOUNIAN
Final 5/23/2024 OK to Issue CofO HAMIK HARTOUNIAN
Service/Power Release 5/23/2024 Approved HAMIK HARTOUNIAN