322-322 1/2 E 33RD ST 90011

Certificate Information: 322-322 1/2 E 33RD ST 90011

Application / Permit
21010-10000-06534
Plan Check / Job No.
B21LA23598
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX (FRONT BUILDING)
Permit Issued
Issued on 7/6/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 MAHNAZ NOURHASHEMI
Corrections Issued 1/1/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 1/7/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 1/13/2022 APPLICANT
Plan Check Approved 4/6/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 7/6/2022 MAHNAZ NOURHASHEMI
Issued 7/6/2022 APPLICANT
CofO in Progress 12/24/2022 ALEJANDRO DE ARTOLA
Permit Finaled 12/31/2022 DEROLD HAUFF
CofO Issued 12/31/2022 DEROLD HAUFF
Permit Finaled 12/31/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/24/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/27/2022 TREVOR QUAN
Sewer availability Cleared 1/27/2022 TREVOR QUAN
Hydrant and Access approval Cleared 3/10/2022 LARRY REDDEN
Low Impact Development Cleared 3/29/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/4/2022 TREVOR QUAN

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/21/2022 Conditional Approval ALEJANDRO DE ARTOLA
Underground Mechanical 7/28/2022 Partial Approval JOAQUIN GREENOUGH
Wood Frame 7/28/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/29/2022 Partial Approval JOAQUIN GREENOUGH
Insulation 7/29/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 9/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/12/2022 Corrections Issued SHAVONNE ESPINOZA
Green Building Rough 9/12/2022 Not Ready for Inspection SHAVONNE ESPINOZA
HVAC-Rough 9/12/2022 Approved SHAVONNE ESPINOZA
Verify Sprinkler Sign Off 9/12/2022 Approved SHAVONNE ESPINOZA
BUILDING-Rough-Frame 9/14/2022 Conditional Approval ALEJANDRO DE ARTOLA
Green Building Rough 9/14/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/14/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/22/2022 Approved ALEJANDRO DE ARTOLA
Insulation 9/22/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/5/2022 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/5/2022 Approved ALEJANDRO DE ARTOLA
Sewer 10/28/2022 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 10/28/2022 Approved ALEJANDRO DE ARTOLA
Sewer 10/31/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/13/2022 Partial Approval BRENDAN MORELLI
ELECTRICAL-Final 12/22/2022 Approved ALEJANDRO DE ARTOLA
Final 12/22/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/22/2022 Approved ALEJANDRO DE ARTOLA
Gas Test 12/22/2022 Approved ALEJANDRO DE ARTOLA
Green Building Final 12/22/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/22/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 12/22/2022 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/22/2022 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 12/22/2022 Approved ALEJANDRO DE ARTOLA
Final 12/23/2022 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 12/23/2022 Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/23/2022 Approved ALEJANDRO DE ARTOLA