524-524 1/2 N COMMONWEALTH AVE 90004

Certificate Information: 524-524 1/2 N COMMONWEALTH AVE 90004

Application / Permit
21010-10000-06494
Plan Check / Job No.
B21LA23438
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2 DETACHED ADUs PER MULTIPLE ADUs STATE LAW (1-STORY)
Permit Issued
Issued on 7/20/2022
Issuing Office
Current Status
CofO Issued on 10/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2021 APPLICANT
Assigned to Plan Check Engineer 12/23/2021 CARLOS MONTES
Corrections Issued 12/24/2021 CARLOS MONTES
Quality Review Completed 12/27/2021 PRANITA SHAH
Applicant returned to address corrections 4/19/2022 CARLOS MONTES
Applicant returned to address corrections 6/22/2022 CARLOS MONTES
Plan Check Approved 7/14/2022 CARLOS MONTES
Issued 7/20/2022 APPLICANT
CofO in Progress 9/22/2023 FREDDIE RIVERA
CofO in Progress 9/25/2023 FREDDIE RIVERA
Permit Finaled 10/3/2023 DEROLD HAUFF
CofO Issued 10/3/2023 DEROLD HAUFF
Permit Finaled 10/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/20/2022 THAN WIN
Eng Process Fee Ord 176,300 Cleared 1/20/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 1/20/2022 CHRISTOPHER ROCHA
Tenant Habitability Plan Cleared 1/20/2022 PHILLIP MUNGUIA
Grading Pre-Inspection Cleared 1/21/2022 VASIL MIHALEV
Low Impact Development Cleared 5/19/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 5/26/2022 AMAAN MALIK
GPI Written Notices Cleared 7/13/2022 ROBERT HUGHES

Contact Information

Architect Lee,, Wan; Lic. No.: C30792 3442 DESCANSO DRIVE      LOS ANGELES, CA 90026
Contractor L C Construction & Plumbing Corp; Lic. No.: 538151-B       ,
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/31/2022 Partial Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 9/7/2022 Approved FREDDIE RIVERA
Footing/Foundation/Slab 9/7/2022 Approved FREDDIE RIVERA
ELECTRICAL-Rough 11/4/2022 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 11/4/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 11/4/2022 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 11/4/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 11/4/2022 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 11/4/2022 Approved ALIZAH MAYAGOITIA
Underground Mechanical 11/30/2022 Partial Approval CALEB MEISTER
BUILDING-Rough-Frame 1/10/2023 Approved FREDDIE RIVERA
Green Building Rough 1/10/2023 Approved FREDDIE RIVERA
Insulation 1/23/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 1/23/2023 Partial Approval FREDDIE RIVERA
Drywall Nailing 1/31/2023 Corrections Issued FREDDIE RIVERA
Drywall Nailing 2/2/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 2/2/2023 Approved FREDDIE RIVERA
Shower Pan 2/2/2023 Partial Inspection FREDDIE RIVERA
Service/Power Release 5/12/2023 Partial Inspection FREDDIE RIVERA
Final 7/3/2023 Corrections Issued FREDDIE RIVERA
Green Building Final 7/3/2023 Approved FREDDIE RIVERA
MERV13>=Final 7/3/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/3/2023 SGSOV Approved FREDDIE RIVERA
Service/Power Release 7/3/2023 Approved FREDDIE RIVERA
Smoke Detectors 7/3/2023 Approved FREDDIE RIVERA
Final 7/28/2023 Corrections Issued FREDDIE RIVERA
Final 8/25/2023 Conditional Approval FREDDIE RIVERA
Final 9/22/2023 OK to Issue CofO FREDDIE RIVERA