3518 E HUNTER ST 90023
Certificate Information: 3518 E HUNTER ST 90023
- Application / Permit
- 21010-10000-06490
- Plan Check / Job No.
- B21LA23437
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU. (N) 274sf two story detached ADU to back yard of (E) single family residence.
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- CofO Issued on 2/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 1/20/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 1/31/2022 | MICHAEL PEREZ |
| Plan Check Approved | 7/12/2022 | ARSALAN SHABESTARI |
| Issued | 7/22/2022 | APPLICANT |
| CofO in Progress | 1/31/2023 | FREDDIE RIVERA |
| Permit Finaled | 2/4/2023 | DEROLD HAUFF |
| CofO Issued | 2/4/2023 | DEROLD HAUFF |
| Permit Finaled | 2/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 6/14/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2022 | JEANIE LAM |
| Sewer availability | Cleared | 6/15/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/3/2022 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/11/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/7/2022 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 9/7/2022 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 9/7/2022 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/19/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/19/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/19/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/19/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 9/19/2022 | Approved | FREDDIE RIVERA |
| Sewer | 9/19/2022 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 9/19/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/28/2022 | Conditional Approval | FREDDIE RIVERA |
| Insulation | 10/5/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/5/2022 | Partial Inspection | FREDDIE RIVERA |
| Drywall Nailing | 10/14/2022 | Approved | FREDDIE RIVERA |
| Final | 12/12/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 12/12/2022 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/12/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 12/12/2022 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 12/12/2022 | Approved | FREDDIE RIVERA |
| Final | 12/23/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 12/23/2022 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 12/29/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 12/29/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 1/3/2023 | Conditional Approval | FREDDIE RIVERA |
| Final | 1/31/2023 | OK to Issue CofO | FREDDIE RIVERA |