3518 E HUNTER ST 90023

Certificate Information: 3518 E HUNTER ST 90023

Application / Permit
21010-10000-06490
Plan Check / Job No.
B21LA23437
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU. (N) 274sf two story detached ADU to back yard of (E) single family residence.
Permit Issued
Issued on 7/22/2022
Issuing Office
Current Status
CofO Issued on 2/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 ARSALAN SHABESTARI
Corrections Issued 1/20/2022 ARSALAN SHABESTARI
Quality Review Completed 1/31/2022 MICHAEL PEREZ
Plan Check Approved 7/12/2022 ARSALAN SHABESTARI
Issued 7/22/2022 APPLICANT
CofO in Progress 1/31/2023 FREDDIE RIVERA
Permit Finaled 2/4/2023 DEROLD HAUFF
CofO Issued 2/4/2023 DEROLD HAUFF
Permit Finaled 2/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/14/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 6/14/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/15/2022 JEANIE LAM
Sewer availability Cleared 6/15/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/3/2022 Approved MICHAEL LEWIS
Footing/Foundation/Slab 8/11/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 9/7/2022 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Inspection FREDDIE RIVERA
Green Building Rough 9/7/2022 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 9/7/2022 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/19/2022 Approved FREDDIE RIVERA
ELECTRICAL-Rough 9/19/2022 Approved FREDDIE RIVERA
Green Building Rough 9/19/2022 Approved FREDDIE RIVERA
HVAC-Rough 9/19/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 9/19/2022 Approved FREDDIE RIVERA
Sewer 9/19/2022 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 9/19/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 9/28/2022 Conditional Approval FREDDIE RIVERA
Insulation 10/5/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/5/2022 Partial Inspection FREDDIE RIVERA
Drywall Nailing 10/14/2022 Approved FREDDIE RIVERA
Final 12/12/2022 Corrections Issued FREDDIE RIVERA
Green Building Final 12/12/2022 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/12/2022 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 12/12/2022 Approved FREDDIE RIVERA
Smoke Detectors 12/12/2022 Approved FREDDIE RIVERA
Final 12/23/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 12/23/2022 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/23/2022 SGSOV Not Ready FREDDIE RIVERA
Final 12/29/2022 Conditional Approval ALIZAH MAYAGOITIA
Green Building Final 12/29/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Approved ALIZAH MAYAGOITIA
Final 1/3/2023 Conditional Approval FREDDIE RIVERA
Final 1/31/2023 OK to Issue CofO FREDDIE RIVERA