4061 3/4 S BUDLONG AVE 90037
Certificate Information: 4061 3/4 S BUDLONG AVE 90037
- Application / Permit
- 21010-10000-06475
- Plan Check / Job No.
- B21LA23387
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY 14'-7" X 34' A.D.U. PER STATE LAW.
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- Current Status
- CofO Issued on 2/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 12/18/2021 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 12/23/2021 | APPLICANT |
| Plan Check Approved | 2/17/2022 | LAWRENCE QUIRANTE |
| Issued | 2/17/2022 | APPLICANT |
| CofO in Progress | 1/22/2024 | SABAS ALONSO |
| Permit Finaled | 2/1/2024 | DEROLD HAUFF |
| CofO Issued | 2/1/2024 | DEROLD HAUFF |
| Permit Finaled | 2/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2021 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 12/27/2021 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2021 | ABEL CASILLAS |
| Sewer availability | Cleared | 12/28/2021 | ABEL CASILLAS |
Contact Information
| Contractor | Jerahian Araz; Lic. No.: 1045340-B | 250 N COLLEGE PARK DR F36 UPLAND, CA 91786 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/2/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 6/21/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 6/21/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/21/2022 | Approved | SABAS ALONSO |
| Special/Order Compliance | 7/15/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/20/2022 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Conditional Approval | SABAS ALONSO |
| Green Building Rough | 7/20/2022 | Not Ready for Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 7/20/2022 | Approved | SABAS ALONSO |
| Wood Frame | 7/20/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 8/1/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 8/1/2022 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 8/4/2022 | Approved | SABAS ALONSO |
| Gas Test | 8/4/2022 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 8/4/2022 | Partial Approval | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Not Ready | SABAS ALONSO |
| Green Building Rough | 8/9/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/9/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/10/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 8/10/2022 | Approved | SABAS ALONSO |
| Insulation | 8/15/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 8/26/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 12/16/2022 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Gas Test | 12/19/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/21/2023 | Corrections Issued | DAVID FEILER |
| Special/Order Compliance | 9/21/2023 | Corrections Issued | DAVID FEILER |
| Service/Power Release | 9/22/2023 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 9/27/2023 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Drilled-In Anchors | 10/11/2023 | Conditional Approval | SABAS ALONSO |
| Service/Power Release | 10/11/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 11/8/2023 | Approved | SABAS ALONSO |
| Final | 11/8/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/8/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 11/8/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 11/8/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 11/8/2023 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 11/8/2023 | Approved | SABAS ALONSO |
| Final | 12/19/2023 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 12/19/2023 | Not Ready for Inspection | SABAS ALONSO |
| Final | 1/19/2024 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 1/19/2024 | Approved | SABAS ALONSO |