3942 S MICHAEL AVE 90066

Certificate Information: 3942 S MICHAEL AVE 90066

Application / Permit
21010-10000-06457
Plan Check / Job No.
B21LA23320
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERT (E) DETACHED GARAGE WITH NEW 2ND STORY ADDITION INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 11/7/2022
Issuing Office
Current Status
CofO Issued on 10/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2021 APPLICANT
Assigned to Plan Check Engineer 1/9/2022 KEVIN MORALES
Corrections Issued 1/10/2022 KEVIN MORALES
Quality Review Completed 1/13/2022 EUGENE BARBEAU
Applicant returned to address corrections 3/29/2022 KEVIN MORALES
Applicant returned to address corrections 7/22/2022 KEVIN MORALES
Applicant returned to address corrections 9/21/2022 KEVIN MORALES
Plan Check Approved 10/13/2022 KEVIN MORALES
Issued 11/7/2022 APPLICANT
CofO in Progress 9/29/2023 JESUS RODRIGUEZ
Permit Finaled 10/7/2023 DANIEL ORRANTE
CofO Issued 10/7/2023 DANIEL ORRANTE
Permit Finaled 10/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/11/2022 RAYMOND MUGAMBWA
Eng Process Fee Ord 176,300 Cleared 2/16/2022 RAYMOND MUGAMBWA
Specific Plan Cleared 2/25/2022 EDUARDO HERMOSO
Construction near power lines Cleared 3/31/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 4/6/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 4/7/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor Manchen Construction Inc ; Lic. No.: 1043435-B       ,
Contractor Manchen Construction Inc; Lic. No.: 1043435-B       ,
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/13/2022 Conditional Approval EVAN COOPER
PLUMBING-Rough 12/16/2022 Partial Approval JESUS RODRIGUEZ
Sewer 12/16/2022 Not Ready for Inspection JESUS RODRIGUEZ
Sewer 12/20/2022 Corrections Issued DAVID FEILER
Sewer 12/22/2022 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 12/27/2022 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 12/27/2022 Conditional Approval JESUS RODRIGUEZ
Special/Order Compliance 12/27/2022 Partial Inspection CLAYTON GRAHAM
Deputy Steel/Welding 2/2/2023 Conditional Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 3/9/2023 Conditional Approval JESUS PINEDA
Drywall Nailing 3/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 3/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 3/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 3/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 4/6/2023 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Corrections Issued HERBERT GIRON
Green Building Rough 4/6/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 4/6/2023 Corrections Issued HERBERT GIRON
Underground Mechanical 4/6/2023 Approved HERBERT GIRON
Deputy Wood Construction 4/7/2023 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 4/13/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 4/13/2023 Approved JESUS RODRIGUEZ
Green Building Rough 4/13/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 4/13/2023 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 4/13/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 5/4/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 5/4/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 5/4/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/4/2023 Approved JESUS RODRIGUEZ
Shower Pan 5/4/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 5/5/2023 Approved JESUS RODRIGUEZ
Final 5/5/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 5/5/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/5/2023 Approved JESUS RODRIGUEZ
Insulation 5/11/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 5/12/2023 Approved JESUS RODRIGUEZ
Green Building Rough 5/12/2023 Approved JESUS RODRIGUEZ
Insulation 5/12/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 5/12/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 5/19/2023 Approved HERBERT GIRON
ELECTRICAL-Final 9/12/2023 Corrections Issued JESUS RODRIGUEZ
Final 9/12/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 9/12/2023 Approved JESUS RODRIGUEZ
HVAC-Final 9/12/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 9/12/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Not Required JESUS RODRIGUEZ
Smoke Detectors 9/12/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/29/2023 Approved JESUS RODRIGUEZ
Final 9/29/2023 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 9/29/2023 Approved JESUS RODRIGUEZ