446 N SURFVIEW DR 90272

Certificate Information: 446 N SURFVIEW DR 90272

Application / Permit
21010-10000-06455
Plan Check / Job No.
B21LA23315
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 8/19/2025
Issuing Office
Valley
Current Status
Issued on 8/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/15/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 DANIEL YIP
Corrections Issued 1/6/2022 DANIEL YIP
Quality Review Completed 1/12/2022 KEN GILL
Building Plans Picked Up 1/21/2022 APPLICANT
Applicant returned to address corrections 10/28/2022 DANIEL YIP
Plan Check Approved 8/13/2025 DANIEL YIP
Issued 8/19/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 11/2/2022 JENSON LEE
Address approval Cleared 4/2/2024 DIANA RENTERIA
Eng Process Fee Ord 176,300 Cleared 4/2/2024 DIANA RENTERIA
Street Frontage Cleared 4/2/2024 DIANA RENTERIA
Trees in Parkway Cleared 4/10/2024 ADALBERTO VERA
Low Impact Development Cleared 7/9/2024 MITESH PATEL
Permit Cleared 7/9/2024 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 7/9/2024 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 10/1/2024 JOHN CONNEALLY
Coastal Zone Cleared 12/19/2024 ASHLEY RODARTE
Miscellaneous Cleared 12/19/2024 ASHLEY RODARTE
Excavation more than 5-ft deep Cleared 8/13/2025 CALOSHA APPROVED
GPI Written Notices Cleared 8/13/2025 DANIEL YIP
Grading Pre-Inspection Cleared 8/13/2025 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,
Engineer Durand,, Paul Henri; Lic. No.: S4222 611 N G ST      OXNARD, CA 93030
Engineer Marte,, Julie Anne Dayanghirang; Lic. No.: C84066 PO BOX 1406      GLENDORA, CA 91740

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 3/20/2026 Corrections Issued DANIEL VERA
Deputy Reinf. Concrete 3/24/2026 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/6/2026 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/17/2026 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 5/7/2026 Conditional Approval BOBBY KEY
Deputy Drilled-In Anchors 5/26/2026 Conditional Approval JUAN VALENZUELA