2931-2941 N HUTTON DR 90210
Certificate Information: 2931-2941 N HUTTON DR 90210
- Application / Permit
- 21010-10000-06446
- Plan Check / Job No.
- B21LA23278
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: New Attached 2-story Accessory Dwelling Unit, new 2 car attached Carport and Conversion of existing attached garage to a part of the SFD (Grading & Retaining Walls under separate permit - Applicant to submit separately) (SFD addition under separate permit)
- Permit Issued
- Issued on 9/18/2023
- Issuing Office
- Current Status
- CofO Issued on 7/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | PRANITA SHAH |
| Corrections Issued | 3/29/2022 | PRANITA SHAH |
| Quality Review Completed | 3/30/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/10/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 5/16/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 2/14/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 4/7/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 4/17/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 9/7/2023 | PRANITA SHAH |
| Plan Check Approved | 9/12/2023 | PRANITA SHAH |
| No Progress | 9/12/2023 | PRANITA SHAH |
| Plan Check Approved | 9/14/2023 | PRANITA SHAH |
| No Progress | 9/14/2023 | PRANITA SHAH |
| Plan Check Approved | 9/14/2023 | PRANITA SHAH |
| Issued | 9/18/2023 | APPLICANT |
| CofO in Progress | 6/24/2025 | STEPHANIE SWANSON |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
| CofO Issued | 7/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZI | Cleared | 4/26/2022 | MIGUEL GAMBOA |
| Address approval | Cleared | 5/3/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/3/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/3/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/3/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/3/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/3/2022 | DINAH GARIN |
| Permit | Cleared | 5/3/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2022 | DINAH GARIN |
| Sewer availability | Cleared | 5/6/2022 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 5/20/2022 | KURT CORRAL |
| Trees in Parkway | Cleared | 6/1/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 8/9/2022 | ANTHONY VARGAS |
| Specific Plan | Cleared | 8/9/2022 | OLGA AYALA |
| Roof/Waste drainage to street | Cleared | 8/11/2022 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 4/7/2023 | PRANITA SHAH |
| Grading Pre-Inspection | Cleared | 4/7/2023 | PRANITA SHAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 9/28/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Special/Order Compliance | 9/28/2023 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 10/11/2023 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 10/16/2023 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/31/2023 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 10/31/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/7/2023 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 11/7/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Final | 11/7/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Pre-Inspection | 2/22/2024 | Approved | SEAN HAUPT |
| Deputy Grading | 3/13/2024 | Approved | SEAN HAUPT |
| Pre-Inspection | 3/13/2024 | Approved | SEAN HAUPT |
| Deputy Grading | 3/14/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Grading | 3/18/2024 | Partial Approval | SEAN HAUPT |
| Piling/Pier/Caisson | 3/18/2024 | Corrections Issued | SEAN HAUPT |
| Deputy Grading | 3/19/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 3/20/2024 | Partial Inspection | SEAN HAUPT |
| Deputy Grading | 3/21/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 3/28/2024 | Conditional Approval | SEAN HAUPT |
| Deputy Grading | 4/3/2024 | Conditional Approval | MICHAEL PELHAM |
| Piling/Pier/Caisson | 4/4/2024 | Partial Approval | MICHAEL PELHAM |
| Deputy Grading | 4/5/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 4/8/2024 | Approved | SEAN HAUPT |
| Piling/Pier/Caisson | 4/8/2024 | Partial Approval | SEAN HAUPT |
| Deputy Grading | 4/9/2024 | Approved | ALEXANDER HELFER |
| Deputy Reinf. Concrete | 4/9/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 4/9/2024 | Partial Approval | SEAN HAUPT |
| Deputy Grading | 4/10/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Grading | 4/11/2024 | Conditional Approval | MICHAEL PELHAM |
| Piling/Pier/Caisson | 4/11/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 4/15/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 4/16/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 4/26/2024 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 4/26/2024 | Corrections Issued | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 4/29/2024 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 4/29/2024 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 5/1/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 5/6/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 5/8/2024 | Conditional Approval | MICHAEL PELHAM |
| Green Building Rough | 5/15/2024 | Not Ready for Inspection | SEAN HAUPT |
| Underground Mechanical | 5/15/2024 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Partial Approval | SEAN HAUPT |
| Green Building Rough | 5/29/2024 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 6/12/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/12/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 6/13/2024 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 6/17/2024 | Partial Approval | SEAN HAUPT |
| Insulation | 6/20/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 6/20/2024 | Partial Approval | SEAN HAUPT |
| Drywall Nailing | 6/25/2024 | Partial Approval | SEAN HAUPT |
| Green Building Rough | 6/25/2024 | Not Ready for Inspection | SEAN HAUPT |
| Footing/Foundation/Slab | 6/27/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 7/29/2024 | Partial Approval | SEAN HAUPT |
| Green Building Rough | 7/29/2024 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/3/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/13/2024 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Corrections Issued | SEAN HAUPT |
| Green Building Rough | 9/13/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 9/17/2024 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 10/31/2024 | Not Ready for Inspection | SEAN HAUPT |
| Interior/Exterior Lathing | 11/15/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 12/3/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 12/3/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 12/5/2024 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 12/5/2024 | Approved | SEAN HAUPT |
| Drywall Nailing | 12/23/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 2/10/2025 | Not Ready for Inspection | SEAN HAUPT |
| Final | 2/10/2025 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 2/10/2025 | Not Ready for Inspection | SEAN HAUPT |
| Shower Pan | 2/24/2025 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 3/26/2025 | Corrections Issued | SEAN HAUPT |
| HVAC-Final | 3/26/2025 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 3/26/2025 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Final | 4/1/2025 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 4/1/2025 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 4/4/2025 | Not Ready for Inspection | SEAN HAUPT |
| Final | 4/4/2025 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/4/2025 | SGSOV Not Ready | SEAN HAUPT |
| ELECTRICAL-Final | 4/9/2025 | Approved | SEAN HAUPT |
| Service/Power Release | 4/9/2025 | Approved | SEAN HAUPT |
| Smoke Detectors | 4/9/2025 | Approved | SEAN HAUPT |
| Special/Order Compliance | 4/9/2025 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 6/20/2025 | Approved | STEPHANIE SWANSON |
| Final | 6/20/2025 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/20/2025 | Approved | STEPHANIE SWANSON |
| Green Building Final | 6/20/2025 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 6/20/2025 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Approved | STEPHANIE SWANSON |
| Final | 6/24/2025 | OK to Issue CofO | STEPHANIE SWANSON |