630-630 1/2 W 79TH ST 90044

Certificate Information: 630-630 1/2 W 79TH ST 90044

Application / Permit
21010-10000-06443
Plan Check / Job No.
B21LA23262
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE (REAR BUILDING B). 2 OF 2
Permit Issued
Issued on 7/5/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 KHUONG TRUONG
Corrections Issued 12/28/2021 KHUONG TRUONG
Quality Review Completed 1/6/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 3/25/2022 KHUONG TRUONG
Building Plans Picked Up 3/29/2022 APPLICANT
Issued 7/5/2022 APPLICANT
CofO in Progress 12/2/2022 LILIANA PORTILLO
Permit Finaled 12/14/2022 DEROLD HAUFF
CofO Issued 12/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/19/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/20/2022 JEANIE LAM
Sewer availability Cleared 1/20/2022 JEANIE LAM
Low Impact Development Cleared 1/27/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 1/28/2022 CELINA MORENO
Highway dedication Cleared 2/3/2022 WALLIE JONG
Hydrant and Access approval Cleared 3/6/2022 CINDY JOSSELYN

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/2/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 8/12/2022 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 8/12/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Partial Approval LILIANA PORTILLO
Insulation 8/15/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 10/3/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 10/3/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/7/2022 Conditional Approval LILIANA PORTILLO
HVAC-Rough 10/7/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/12/2022 Approved LILIANA PORTILLO
Insulation 10/12/2022 Approved LILIANA PORTILLO
Drywall Nailing 10/20/2022 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 10/20/2022 Approved LILIANA PORTILLO
Drywall Nailing 10/21/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/21/2022 Partial Approval ALEJANDRO DE ARTOLA
Sewer 10/21/2022 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 10/21/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/16/2022 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 11/23/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/23/2022 Corrections Issued LILIANA PORTILLO
Final 11/23/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 11/23/2022 Approved LILIANA PORTILLO
Green Building Rough 11/23/2022 Approved LILIANA PORTILLO
HVAC-Final 11/23/2022 Approved LILIANA PORTILLO
PLUMBING-Final 11/23/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 11/23/2022 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 11/23/2022 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 11/23/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/28/2022 Approved LILIANA PORTILLO
Final 11/28/2022 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 11/28/2022 Approved LILIANA PORTILLO
Service/Power Release 11/30/2022 Approved LILIANA PORTILLO