630-630 1/2 W 79TH ST 90044
Certificate Information: 630-630 1/2 W 79TH ST 90044
- Application / Permit
- 21010-10000-06443
- Plan Check / Job No.
- B21LA23262
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE (REAR BUILDING B). 2 OF 2
- Permit Issued
- Issued on 7/5/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | KHUONG TRUONG |
| Corrections Issued | 12/28/2021 | KHUONG TRUONG |
| Quality Review Completed | 1/6/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 3/25/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Issued | 7/5/2022 | APPLICANT |
| CofO in Progress | 12/2/2022 | LILIANA PORTILLO |
| Permit Finaled | 12/14/2022 | DEROLD HAUFF |
| CofO Issued | 12/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/19/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2022 | JEANIE LAM |
| Sewer availability | Cleared | 1/20/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 1/27/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/28/2022 | CELINA MORENO |
| Highway dedication | Cleared | 2/3/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 3/6/2022 | CINDY JOSSELYN |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/2/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/12/2022 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 8/12/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2022 | Partial Approval | LILIANA PORTILLO |
| Insulation | 8/15/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/3/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 10/3/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/7/2022 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 10/7/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Approved | LILIANA PORTILLO |
| Insulation | 10/12/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/20/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/20/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/21/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 10/21/2022 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 10/21/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/16/2022 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/23/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/23/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 11/23/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 11/23/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 11/23/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 11/23/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 11/23/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 11/23/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 11/23/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 11/23/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/28/2022 | Approved | LILIANA PORTILLO |
| Final | 11/28/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 11/28/2022 | Approved | LILIANA PORTILLO |
| Service/Power Release | 11/30/2022 | Approved | LILIANA PORTILLO |