7527 S DUNFIELD AVE 90045

Certificate Information: 7527 S DUNFIELD AVE 90045

Application / Permit
21010-10000-06388
Plan Check / Job No.
B21LA23081
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Converting existing 327 Sq.Ft. garage to an ADU
Permit Issued
Issued on 2/8/2022
Issuing Office
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2021 APPLICANT
Assigned to Plan Check Engineer 12/17/2021 JOE VO
Corrections Issued 12/17/2021 JOE VO
Plan Check Approved 1/5/2022 JOE VO
Issued 2/8/2022 APPLICANT
CofO in Progress 1/10/2023 HERBERT GIRON
Permit Finaled 1/18/2023 DANIEL ORRANTE
CofO Issued 1/18/2023 DANIEL ORRANTE
Permit Finaled 1/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/28/2021 DENNIS BRAGIN
Sewer availability Cleared 12/28/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 1/3/2022 DENNIS BRAGIN
Grading Pre-Inspection Cleared 1/5/2022 JOE VO

Contact Information

Contractor United Real Estate Development Inc; Lic. No.: 983140-B 10940 ODELL AVENUE      SUNLAND, CA 91040

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/17/2022 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 3/17/2022 Corrections Issued JESUS RODRIGUEZ
METHANE-Rough 3/17/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 3/17/2022 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 3/17/2022 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/5/2022 Partial Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 5/5/2022 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 5/5/2022 Conditional Approval JESUS RODRIGUEZ
METHANE-Rough 5/5/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/5/2022 Approved JESUS RODRIGUEZ
Sewer 5/5/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 5/5/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/19/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 5/19/2022 Approved BOBBY KEY
HVAC-Rough 5/19/2022 Approved BOBBY KEY
Interior/Exterior Lathing 5/19/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 6/15/2022 Approved RICHARD STEINBACH
Insulation 6/15/2022 Corrections Issued RICHARD STEINBACH
Shower Pan 6/15/2022 Corrections Issued RICHARD STEINBACH
Insulation 6/23/2022 Approved STEPHANIE SWANSON
Drywall Nailing 7/12/2022 Approved JESUS RODRIGUEZ
Shower Pan 7/12/2022 Corrections Issued JESUS RODRIGUEZ
Shower Pan 7/25/2022 Not Ready for Inspection HERBERT GIRON
Shower Pan 8/1/2022 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 8/4/2022 Approved HERBERT GIRON
Shower Pan 8/4/2022 Approved HERBERT GIRON
ELECTRICAL-Final 11/15/2022 Corrections Issued HERBERT GIRON
Final 11/15/2022 Corrections Issued HERBERT GIRON
HVAC-Final 11/15/2022 Corrections Issued HERBERT GIRON
PLUMBING-Final 11/15/2022 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Approved HERBERT GIRON
Smoke Detectors 11/15/2022 Approved HERBERT GIRON
ELECTRICAL-Final 12/2/2022 Approved HERBERT GIRON
Final 12/2/2022 Corrections Issued HERBERT GIRON
Gas Test 12/2/2022 Approved HERBERT GIRON
HVAC-Final 12/2/2022 Corrections Issued HERBERT GIRON
PLUMBING-Final 12/2/2022 Corrections Issued HERBERT GIRON
Final 1/10/2023 OK to Issue CofO HERBERT GIRON
HVAC-Final 1/10/2023 Approved HERBERT GIRON
PLUMBING-Final 1/10/2023 Approved HERBERT GIRON