7527 S DUNFIELD AVE 90045
Certificate Information: 7527 S DUNFIELD AVE 90045
- Application / Permit
- 21010-10000-06388
- Plan Check / Job No.
- B21LA23081
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Converting existing 327 Sq.Ft. garage to an ADU
- Permit Issued
- Issued on 2/8/2022
- Issuing Office
- Current Status
- CofO Issued on 1/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2021 | JOE VO |
| Corrections Issued | 12/17/2021 | JOE VO |
| Plan Check Approved | 1/5/2022 | JOE VO |
| Issued | 2/8/2022 | APPLICANT |
| CofO in Progress | 1/10/2023 | HERBERT GIRON |
| Permit Finaled | 1/18/2023 | DANIEL ORRANTE |
| CofO Issued | 1/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/28/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 12/28/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | DENNIS BRAGIN |
| Grading Pre-Inspection | Cleared | 1/5/2022 | JOE VO |
Contact Information
| Contractor | United Real Estate Development Inc; Lic. No.: 983140-B | 10940 ODELL AVENUE SUNLAND, CA 91040 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/17/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/17/2022 | Corrections Issued | JESUS RODRIGUEZ |
| METHANE-Rough | 3/17/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/17/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Underground Mechanical | 3/17/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/5/2022 | Partial Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/5/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/5/2022 | Conditional Approval | JESUS RODRIGUEZ |
| METHANE-Rough | 5/5/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/5/2022 | Approved | JESUS RODRIGUEZ |
| Sewer | 5/5/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 5/5/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/19/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 5/19/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 5/19/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 5/19/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 6/15/2022 | Approved | RICHARD STEINBACH |
| Insulation | 6/15/2022 | Corrections Issued | RICHARD STEINBACH |
| Shower Pan | 6/15/2022 | Corrections Issued | RICHARD STEINBACH |
| Insulation | 6/23/2022 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 7/12/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 7/12/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 7/25/2022 | Not Ready for Inspection | HERBERT GIRON |
| Shower Pan | 8/1/2022 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 8/4/2022 | Approved | HERBERT GIRON |
| Shower Pan | 8/4/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/15/2022 | Corrections Issued | HERBERT GIRON |
| Final | 11/15/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 11/15/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 11/15/2022 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 11/15/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 12/2/2022 | Approved | HERBERT GIRON |
| Final | 12/2/2022 | Corrections Issued | HERBERT GIRON |
| Gas Test | 12/2/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 12/2/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 12/2/2022 | Corrections Issued | HERBERT GIRON |
| Final | 1/10/2023 | OK to Issue CofO | HERBERT GIRON |
| HVAC-Final | 1/10/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 1/10/2023 | Approved | HERBERT GIRON |