7042 S 3RD AVE 90043
Certificate Information: 7042 S 3RD AVE 90043
- Application / Permit
- 21010-10000-06386
- Plan Check / Job No.
- B21LA23080
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/8/2022
- Issuing Office
- Current Status
- CofO Issued on 4/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | PRANITA SHAH |
| Corrections Issued | 12/17/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 2/1/2022 | PRANITA SHAH |
| Plan Check Approved | 7/29/2022 | DANIEL YIP |
| Issued | 8/8/2022 | APPLICANT |
| CofO in Progress | 4/18/2023 | ENRIQUE MIRELES |
| CofO in Progress | 4/18/2023 | ENRIQUE MIRELES |
| Permit Finaled | 4/29/2023 | DEROLD HAUFF |
| CofO Issued | 4/29/2023 | DEROLD HAUFF |
| Permit Finaled | 4/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 3/23/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 3/29/2022 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 6/3/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/3/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/23/2022 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 8/23/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 10/13/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/13/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 10/24/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/24/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 11/2/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 11/2/2022 | Approved | ENRIQUE MIRELES |
| Piling/Pier/Caisson | 11/2/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/9/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/9/2022 | Corrections Issued | ENRIQUE MIRELES |
| Wood Frame | 12/9/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/16/2022 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/16/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/16/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 12/16/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 12/16/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/21/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 12/21/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/21/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/27/2022 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/30/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/18/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/16/2023 | Approved | ENRIQUE MIRELES |
| Final | 3/16/2023 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/16/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 3/16/2023 | Approved | ENRIQUE MIRELES |
| Final | 3/29/2023 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 3/29/2023 | Approved | ENRIQUE MIRELES |