2223-2223 1/2 E SHERIDAN ST 90033

Certificate Information: 2223-2223 1/2 E SHERIDAN ST 90033

Application / Permit
21010-10000-06378
Plan Check / Job No.
B21LA23073
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
[CUGU-PUBLICLY HABITABLE SPACE] (N) 3-STORY DUPLEX (FRONT BLDG)
Permit Issued
Issued on 6/29/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 KHEDER ALRAZAA
Corrections Issued 12/28/2021 KHEDER ALRAZAA
Quality Review Completed 1/11/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 1/18/2022 APPLICANT
Applicant returned to address corrections 7/29/2022 KHEDER ALRAZAA
Applicant returned to address corrections 9/6/2022 KHEDER ALRAZAA
Plan Check Approved 6/29/2023 KHEDER ALRAZAA
Issued 6/29/2023 APPLICANT
CofO in Progress 5/13/2025 ALIZAH MAYAGOITIA
No Progress 5/17/2025 DEROLD HAUFF
CofO in Progress 5/17/2025 DEROLD HAUFF
Permit Finaled 6/6/2025 DEROLD HAUFF
CofO Issued 6/6/2025 DEROLD HAUFF
Permit Finaled 6/6/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/6/2022 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 1/25/2022 KHOUNG LE
Sewer availability Cleared 1/25/2022 KHOUNG LE
Hydrant and Access approval Cleared 3/24/2022 JOHN CONNEALLY
Clean Up Green Up Cleared 3/30/2022 MIGUEL GAMBOA
Frnt yard landscape/Water mgmt Cleared 4/4/2022 MIGUEL GAMBOA
Trees in Parkway Cleared 4/19/2022 ADALBERTO VERA
Highway dedication Cleared 5/3/2022 KHOUNG LE
Permit Cleared 5/3/2022 KHOUNG LE
GPI Written Notices Cleared 5/10/2022 KHEDER ALRAZAA
Grading Pre-Inspection Cleared 5/10/2022 KHEDER ALRAZAA
Low Impact Development Cleared 5/13/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/17/2022 KHOUNG LE
DAS Clearance Cleared 1/17/2023 SHINE LIN

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 669 N THIRD AVENUE      UPLAND, CA 91786
Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/1/2023 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 11/1/2023 Not Ready for Inspection OSVALDO PARAMO
Underground Mechanical 11/1/2023 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 11/7/2023 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 11/14/2023 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 11/21/2023 Approved OSVALDO PARAMO
Footing/Foundation/Slab 11/21/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 4/22/2024 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Approved OSVALDO PARAMO
ELECTRICAL-Rough 8/5/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 8/5/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 8/7/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 8/7/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 8/7/2024 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 8/7/2024 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 8/7/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/20/2024 Approved OSVALDO PARAMO
PLUMBING-Rough 8/20/2024 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 8/20/2024 Approved OSVALDO PARAMO
Insulation 8/26/2024 Approved LUIS CASTRO
Drywall Nailing 9/5/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 9/5/2024 Approved LUIS CASTRO
Gas Test 11/5/2024 Partial Approval OSVALDO PARAMO
Sewer 11/5/2024 Approved OSVALDO PARAMO
Underground Mechanical 11/5/2024 Partial Approval OSVALDO PARAMO
Underground Mechanical 11/14/2024 Approved JOSH MEISTER
ELECTRICAL-Final 4/2/2025 Approved ALIZAH MAYAGOITIA
Gas Test 4/2/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 4/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 4/2/2025 Approved ALIZAH MAYAGOITIA
Smoke Detectors 4/2/2025 Approved ALIZAH MAYAGOITIA
Verify Rec and Parks Fee Memo 4/2/2025 Approved ALIZAH MAYAGOITIA
Final 5/2/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 5/2/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 5/2/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Final 5/2/2025 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 5/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 5/8/2025 Approved ALIZAH MAYAGOITIA
Final 5/8/2025 Conditional Approval ALIZAH MAYAGOITIA
MERV13>=Final 5/8/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 5/8/2025 Approved ALIZAH MAYAGOITIA
Final 5/13/2025 OK to Issue CofO ALIZAH MAYAGOITIA