2223-2223 1/2 E SHERIDAN ST 90033
Certificate Information: 2223-2223 1/2 E SHERIDAN ST 90033
- Application / Permit
- 21010-10000-06378
- Plan Check / Job No.
- B21LA23073
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- [CUGU-PUBLICLY HABITABLE SPACE] (N) 3-STORY DUPLEX (FRONT BLDG)
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | KHEDER ALRAZAA |
| Corrections Issued | 12/28/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 1/11/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/18/2022 | APPLICANT |
| Applicant returned to address corrections | 7/29/2022 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 9/6/2022 | KHEDER ALRAZAA |
| Plan Check Approved | 6/29/2023 | KHEDER ALRAZAA |
| Issued | 6/29/2023 | APPLICANT |
| CofO in Progress | 5/13/2025 | ALIZAH MAYAGOITIA |
| No Progress | 5/17/2025 | DEROLD HAUFF |
| CofO in Progress | 5/17/2025 | DEROLD HAUFF |
| Permit Finaled | 6/6/2025 | DEROLD HAUFF |
| CofO Issued | 6/6/2025 | DEROLD HAUFF |
| Permit Finaled | 6/6/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2022 | KHOUNG LE |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2022 | KHOUNG LE |
| Sewer availability | Cleared | 1/25/2022 | KHOUNG LE |
| Hydrant and Access approval | Cleared | 3/24/2022 | JOHN CONNEALLY |
| Clean Up Green Up | Cleared | 3/30/2022 | MIGUEL GAMBOA |
| Frnt yard landscape/Water mgmt | Cleared | 4/4/2022 | MIGUEL GAMBOA |
| Trees in Parkway | Cleared | 4/19/2022 | ADALBERTO VERA |
| Highway dedication | Cleared | 5/3/2022 | KHOUNG LE |
| Permit | Cleared | 5/3/2022 | KHOUNG LE |
| GPI Written Notices | Cleared | 5/10/2022 | KHEDER ALRAZAA |
| Grading Pre-Inspection | Cleared | 5/10/2022 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 5/13/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/17/2022 | KHOUNG LE |
| DAS Clearance | Cleared | 1/17/2023 | SHINE LIN |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/1/2023 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/1/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Underground Mechanical | 11/1/2023 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 11/7/2023 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/14/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 11/21/2023 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/21/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | Partial Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 4/22/2024 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 8/5/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/5/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/7/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/7/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/7/2024 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 8/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 8/7/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/20/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 8/20/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 8/20/2024 | Approved | OSVALDO PARAMO |
| Insulation | 8/26/2024 | Approved | LUIS CASTRO |
| Drywall Nailing | 9/5/2024 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 9/5/2024 | Approved | LUIS CASTRO |
| Gas Test | 11/5/2024 | Partial Approval | OSVALDO PARAMO |
| Sewer | 11/5/2024 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 11/5/2024 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 11/14/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 4/2/2025 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 4/2/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 4/2/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/2/2025 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/2/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Rec and Parks Fee Memo | 4/2/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/2/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 5/2/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/2/2025 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Final | 5/2/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 5/2/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 5/2/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 5/8/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/8/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| MERV13>=Final | 5/8/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 5/8/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/13/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |