2724 E EAGLE ST 90033
Certificate Information: 2724 E EAGLE ST 90033
- Application / Permit
- 21010-10000-06374
- Plan Check / Job No.
- B21LA23055
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED DETACHED 2-STORY ADU WITH 2-CAR CARPORT AT 1ST FLOOR. ADU PER LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 8/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | ADRIANA LOPEZ |
| Corrections Issued | 1/19/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 1/19/2022 | KEN GILL |
| Building Plans Picked Up | 1/25/2022 | APPLICANT |
| Applicant returned to address corrections | 5/13/2022 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 5/27/2022 | ADRIANA LOPEZ |
| Plan Check Approved | 5/27/2022 | ADRIANA LOPEZ |
| Issued | 8/9/2022 | APPLICANT |
| CofO in Progress | 2/8/2024 | FREDDIE RIVERA |
| Permit Finaled | 2/12/2024 | DEROLD HAUFF |
| CofO Issued | 2/12/2024 | DEROLD HAUFF |
| Permit Finaled | 2/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 1/27/2022 | ABEL CASILLAS |
| Clean Up Green Up | Cleared | 1/31/2022 | ANACANY HURTADO |
| Low Impact Development | Cleared | 3/18/2022 | ANTHONY VARGAS |
| Tenant Habitability Plan | Cleared | 3/23/2022 | MICHAEL SOTO |
| Grading Pre-Inspection | Cleared | 4/1/2022 | ROBERT HUGHES |
| GPI Written Notices | Cleared | 5/13/2022 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 5/17/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mejia,, Fernando Finuliar; Lic. No.: C54382 | 8305 DUCOR AVE WEST HILLS, CA 91304 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 9/12/2022 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 9/12/2022 | Partial Inspection | FREDDIE RIVERA |
| Pre-Inspection | 9/12/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/26/2022 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Barrier | 9/26/2022 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 9/26/2022 | Corrections Issued | FREDDIE RIVERA |
| Sewer | 9/26/2022 | Partial Inspection | FREDDIE RIVERA |
| Sewer | 9/27/2022 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Partial Approval | JOSE AVILA |
| METHANE-Barrier | 11/1/2022 | Approved | JOSE AVILA |
| Reinforced Concrete Frame | 11/1/2022 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 11/23/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 11/23/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| Underground Mechanical | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 11/23/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/30/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 11/30/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 11/30/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 11/30/2022 | Approved | FREDDIE RIVERA |
| Insulation | 12/13/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 12/13/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Shower Pan | 12/13/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 12/28/2022 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 12/30/2022 | Approved | RUBEN SALAS |
| Drywall Nailing | 1/4/2023 | Partial Approval | FREDDIE RIVERA |
| Shower Pan | 2/10/2023 | Approved | FREDDIE RIVERA |
| Sewer | 3/6/2023 | Corrections Issued | FREDDIE RIVERA |
| Sewer | 3/24/2023 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 4/4/2023 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 6/6/2023 | Approved | FREDDIE RIVERA |
| Final | 6/6/2023 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/6/2023 | Approved | FREDDIE RIVERA |
| Green Building Final | 6/6/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 6/6/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 6/6/2023 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 6/6/2023 | Approved | FREDDIE RIVERA |
| Final | 6/21/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 6/21/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 6/21/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 7/3/2023 | Approved | FREDDIE RIVERA |
| Final | 7/3/2023 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 7/3/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 12/14/2023 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/14/2023 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 12/14/2023 | Approved | FREDDIE RIVERA |
| Final | 2/1/2024 | Corrections Issued | FREDDIE RIVERA |
| Final | 2/8/2024 | OK to Issue CofO | FREDDIE RIVERA |