6336-6336 1/2 N BECK AVE 91606
Certificate Information: 6336-6336 1/2 N BECK AVE 91606
- Application / Permit
- 21010-10000-06369
- Plan Check / Job No.
- B21LA23045
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX WITH ATTACHED 2 CAR GARAGE (MIDDLE BLDG)
- Permit Issued
- Issued on 9/22/2022
- Issuing Office
- Current Status
- CofO Issued on 4/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | KHEDER ALRAZAA |
| Corrections Issued | 12/26/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 1/4/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/14/2022 | APPLICANT |
| Green Plans Picked Up | 2/7/2022 | APPLICANT |
| Applicant returned to address corrections | 7/29/2022 | KHEDER ALRAZAA |
| Plan Check Approved | 9/13/2022 | KHEDER ALRAZAA |
| Issued | 9/22/2022 | APPLICANT |
| CofO in Progress | 2/10/2025 | JOSE AVILA |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
| CofO Issued | 4/1/2025 | RUBEN SALAS |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2022 | WALLIE JONG |
| "Q" conditions | Cleared | 1/13/2022 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2022 | WALLIE JONG |
| Sewer availability | Cleared | 2/10/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 4/21/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 6/9/2022 | TA ANH |
| Frnt yard landscape/Water mgmt | Cleared | 7/7/2022 | DALIA MOKAYED |
| Opn space landscape/Water mgmt | Cleared | 7/7/2022 | DALIA MOKAYED |
| Roof/Waste drainage to street | Cleared | 7/19/2022 | LEE GUILBEAUX |
| Highway dedication | Cleared | 8/17/2022 | LEE GUILBEAUX |
| Permit | Cleared | 9/9/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Unit Builders Inc; Lic. No.: 1071723-B | P O BOX 90902 LONG BEACH, CA 90809 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/30/2022 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 12/13/2022 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 12/28/2022 | Not Ready for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 12/30/2022 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 1/23/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 11/3/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/3/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 11/20/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/20/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/7/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 12/7/2023 | Approved | JOHN HAYES |
| Green Building Rough | 12/7/2023 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 12/7/2023 | Approved | JOHN HAYES |
| Insulation | 1/9/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 1/16/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 1/16/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 9/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 9/18/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 9/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 9/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 10/28/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 10/28/2024 | Approved | RAUL OLAGI |
| PLUMBING-Final | 10/28/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/23/2024 | Approved | JOSE AVILA |
| Final | 1/7/2025 | Not Ready for Inspection | JOSE AVILA |
| Green Building Final | 1/7/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 1/7/2025 | Approved | JOSE AVILA |
| Final | 2/7/2025 | OK to Issue CofO | JOSE AVILA |
| Footing/Foundation/Slab | 2/7/2025 | Approved | JOSE AVILA |
| Service/Power Release | 2/7/2025 | Approved | JOSE AVILA |