945 S CATALINA ST 90006
Certificate Information: 945 S CATALINA ST 90006
- Application / Permit
- 21010-10000-06338
- Plan Check / Job No.
- B21LA22952
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW ACCESSORY DWELLING UNIT ATTACHED TO (E) DETACHED GARAGE PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 7/21/2022
- Issuing Office
- Current Status
- CofO Issued on 10/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2021 | KEVIN MORALES |
| Corrections Issued | 12/31/2021 | KEVIN MORALES |
| Quality Review Completed | 1/6/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 5/10/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 5/26/2022 | KEVIN MORALES |
| Plan Check Approved | 7/18/2022 | KEVIN MORALES |
| Issued | 7/21/2022 | APPLICANT |
| CofO in Progress | 10/5/2023 | NICK DANERI |
| Permit Finaled | 10/10/2023 | ERNESTO CORRAL |
| CofO Issued | 10/10/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 1/7/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 1/7/2022 | JEANETTE VONG |
| Historic Resource Verification | Cleared | 1/11/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 1/28/2022 | GRACIELA ACOSTA |
| Construction within easement | Cleared | 3/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD 230 TARZANA, CA 91356 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/18/2022 | Not Ready for Inspection | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 8/25/2022 | Corrections Issued | NICK DANERI |
| Footing/Foundation/Slab | 8/25/2022 | No Access for Inspection | NICK DANERI |
| Footing/Foundation/Slab | 9/20/2022 | Not Ready for Inspection | NICK DANERI |
| Pre-Inspection | 9/22/2022 | Partial Approval | NICK DANERI |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Not Ready for Inspection | GREGORY POMISH |
| Green Building Rough | 10/24/2022 | Not Ready for Inspection | GREGORY POMISH |
| Pre-Inspection | 10/24/2022 | Not Ready for Inspection | GREGORY POMISH |
| Wood Frame | 10/24/2022 | Not Ready for Inspection | GREGORY POMISH |
| Green Building Rough | 10/31/2022 | Not Ready for Inspection | NICK DANERI |
| Wood Frame | 10/31/2022 | Not Ready for Inspection | NICK DANERI |
| Green Building Rough | 11/18/2022 | Not Ready for Inspection | NICK DANERI |
| Wood Frame | 11/18/2022 | Corrections Issued | NICK DANERI |
| Green Building Rough | 11/30/2022 | Not Ready for Inspection | NICK DANERI |
| Wood Frame | 11/30/2022 | Partial Inspection | NICK DANERI |
| Deputy Wood Construction | 12/1/2022 | Conditional Approval | NICK DANERI |
| Pre-Inspection | 12/1/2022 | Partial Approval | NICK DANERI |
| Deputy Wood Construction | 12/7/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Insulation | 12/7/2022 | Partial Approval | NICK DANERI |
| Interior/Exterior Lathing | 12/7/2022 | Partial Approval | NICK DANERI |
| Drywall Nailing | 12/13/2022 | Approved | GREGORY POMISH |
| Final | 8/29/2023 | Not Ready for Inspection | NICK DANERI |
| Footing/Foundation/Slab | 8/29/2023 | Approved | NICK DANERI |
| Green Building Final | 8/29/2023 | Not Ready for Inspection | NICK DANERI |
| Green Building Rough | 8/29/2023 | Approved | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Not Ready | NICK DANERI |
| Smoke Detectors | 8/29/2023 | Not Ready for Inspection | NICK DANERI |
| Wood Frame | 8/29/2023 | Approved | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Not Ready | NICK DANERI |
| Pre-Inspection | 9/5/2023 | Corrections Issued | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 9/6/2023 | SGSOV Not Ready | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 9/8/2023 | SGSOV Not Ready | NICK DANERI |
| Final | 9/12/2023 | Not Ready for Inspection | NICK DANERI |
| Green Building Final | 9/12/2023 | Approved | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Approved | NICK DANERI |
| Smoke Detectors | 9/12/2023 | Approved | NICK DANERI |
| Final | 9/27/2023 | Not Ready for Inspection | NICK DANERI |
| Final | 10/4/2023 | OK to Issue CofO | NICK DANERI |