4000 W MONT CLAIR ST 1-15 90018

Certificate Information: 4000 W MONT CLAIR ST 1-15 90018

Application / Permit
21010-10000-06322
Plan Check / Job No.
B21LA22889
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4-STORY 15 UNIT APARTMENT BUILDING OVER PARKING GARAGE.
Permit Issued
Issued on 12/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2021 APPLICANT
Green Plans Picked Up 12/14/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 ARMEN JIVALAGIAN
Corrections Issued 12/23/2021 ARMEN JIVALAGIAN
Quality Review Completed 12/23/2021 PETER KIM
Building Plans Picked Up 1/3/2022 APPLICANT
Disabled Access Plans Picked Up 1/11/2022 APPLICANT
Applicant returned to address corrections 3/25/2022 ARMEN JIVALAGIAN
Applicant returned to address corrections 4/15/2022 ARMEN JIVALAGIAN
Applicant returned to address corrections 5/20/2022 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/20/2022 ARMEN JIVALAGIAN
Plan Check Approved 11/3/2022 ARMEN JIVALAGIAN
Issued 12/29/2022 APPLICANT
TCO Issued (Expire Date: 11-01-2025) 5/5/2025 ERNESTO CORRAL
CofO in Progress 9/15/2025 JAMES POWERS
Permit Finaled 9/15/2025 ERNESTO CORRAL
CofO Issued 9/15/2025 ERNESTO CORRAL
Permit Finaled 9/15/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 2/16/2022 TREVOR QUAN
Highway dedication Cleared 2/16/2022 TREVOR QUAN
Permit Cleared 2/22/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/23/2022 TREVOR QUAN
Sewer availability Cleared 2/23/2022 TREVOR QUAN
Hydrant and Access approval Cleared 3/23/2022 GILBERT URREA
Green Code Cleared 3/24/2022 AARON COSTA
Tract Map conditions Cleared 4/28/2022 RYAN LY
Trees in Parkway Cleared 4/28/2022 ADALBERTO VERA
Low Impact Development Cleared 5/4/2022 AMMAR ELTAWIL
Frnt yard landscape/Water mgmt Cleared 5/10/2022 JASON CHAN
Opn space landscape/Water mgmt Cleared 5/10/2022 JASON CHAN
Roof/Waste drainage to street Cleared 5/10/2022 STEVE MELGAR
Fire Marshal Fire Life Safety Cleared 5/23/2022 OSCAR SALGADO JR
Building over 36-ft Cleared 5/26/2022 CALOSHA APPROVED
DAS Clearance Cleared 9/8/2022 ARMEN JIVALAGIAN

Contact Information

Architect Park,, Jay H.; Lic. No.: C36800 3850 WILSHIRE BLVD #308      LOS ANGELES, CA 90010
Contractor B & Sons Construction Inc; Lic. No.: 1066259-B 4361 E MISSION BLVD #37      MONTCLAIR, CA 91763
Engineer Kim,, Seung Su; Lic. No.: S5909 15808 APOLLO PLACE      GARDENA, CA 90249
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/20/2023 Not Ready for Inspection GREGORY POMISH
Pre-Inspection 4/20/2023 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 5/3/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/17/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 6/8/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 6/15/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/28/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/25/2023 Not Ready for Inspection JAMES POWERS
Masonry Wall/Backfill 8/25/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/4/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 10/4/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 12/12/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/28/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 1/17/2024 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 1/17/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 1/17/2024 Partial Approval JAMES POWERS
Insulation 1/25/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/25/2024 Partial Approval JAMES POWERS
Insulation 1/29/2024 Partial Approval JAMES POWERS
Insulation 2/6/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/22/2024 Partial Approval JAMES POWERS
Drywall Nailing 2/27/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/7/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/15/2024 Approved JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Partial Approval JAMES POWERS
Final 4/8/2025 OK for TCO JAMES POWERS
Footing/Foundation/Slab 4/8/2025 Approved JAMES POWERS
Green Building Final 4/8/2025 Approved JAMES POWERS
Green Building Rough 4/8/2025 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Approved JAMES POWERS
Smoke Detectors 4/8/2025 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 4/8/2025 Approved JAMES POWERS
Wood Frame 4/8/2025 Approved JAMES POWERS
Wood Frame 7/21/2025 Partial Approval JAMES POWERS
Drywall Nailing 7/23/2025 Partial Approval JAMES POWERS
Final 8/28/2025 Not Ready for Inspection JAMES POWERS
Smoke Detectors 8/28/2025 Approved JAMES POWERS
Wood Frame 8/28/2025 Approved JAMES POWERS
Deputy Reinf. Concrete 9/15/2025 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/15/2025 Partial Approval JAMES POWERS
Final 9/15/2025 OK to Issue CofO JAMES POWERS