1360 W 35TH ST 90007
Certificate Information: 1360 W 35TH ST 90007
- Application / Permit
- 21010-10000-06321
- Plan Check / Job No.
- B21LA22886
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 4-STORY SFD.
- Permit Issued
- Issued on 10/11/2022
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 12/27/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/6/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 9/12/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 10/11/2022 | MAHNAZ NOURHASHEMI |
| Issued | 10/11/2022 | APPLICANT |
| CofO in Progress | 8/23/2024 | SABAS ALONSO |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | JEANIE LAM |
| Frnt yard landscape/Water mgmt | Cleared | 2/22/2022 | DANIEL CORONADO |
| ZI | Cleared | 3/15/2022 | DANIEL CORONADO |
| Low Impact Development | Cleared | 4/1/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 4/12/2022 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 8/16/2022 | ROBERT DUFF |
| Building over 36-ft | Cleared | 9/12/2022 | CALOSHA APPROVED |
| Sewer availability | Cleared | 9/12/2022 | TREVOR QUAN |
Contact Information
| Contractor | Tre Development Llc; Lic. No.: 1075573-B | 2905 S VERMONT AVE #204 LOS ANGELES, CA 90007 |
| Engineer | Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 | PO BOX 5044 PASADENA, CA 91117 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 3/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 4/11/2023 | Partial Approval | SABAS ALONSO |
| Sewer | 4/18/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/18/2023 | Approved | SABAS ALONSO |
| Deputy Methane Barrier | 4/25/2023 | Conditional Approval | SABAS ALONSO |
| METHANE-Subgrade | 4/26/2023 | Approved | SABAS ALONSO |
| Deputy Methane Barrier | 5/10/2023 | Conditional Approval | SABAS ALONSO |
| Deputy Reinf. Concrete | 5/12/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 5/15/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 5/15/2023 | Approved | SABAS ALONSO |
| METHANE-Barrier | 5/15/2023 | Approved | SABAS ALONSO |
| Deputy Wood Construction | 6/13/2023 | Approved | DONALD CRICHLOW |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 7/11/2023 | Conditional Approval | CHARLES BOGHOSKHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 7/31/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2023 | Partial Approval | SABAS ALONSO |
| HVAC-Rough | 9/14/2023 | No Access for Inspection | SABAS ALONSO |
| HVAC-Rough | 9/21/2023 | Approved | SABAS ALONSO |
| METHANE-Rough | 9/21/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 9/21/2023 | Approved | SABAS ALONSO |
| Shower Pan | 9/21/2023 | Approved | SABAS ALONSO |
| Deputy Wood Construction | 9/22/2023 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/30/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 11/3/2023 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 11/7/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 12/29/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/8/2024 | Corrections Issued | SABAS ALONSO |
| Verify Sprinkler Sign Off | 1/8/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/23/2024 | Approved | SABAS ALONSO |
| Insulation | 1/23/2024 | Approved | SABAS ALONSO |
| Insulation | 3/7/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 3/26/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/5/2024 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 6/13/2024 | Not Ready for Inspection | JOSH MEISTER |
| Underground Mechanical | 7/2/2024 | Partial Approval | JOSH MEISTER |
| Final | 7/31/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 7/31/2024 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 7/31/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 7/31/2024 | Approved | SABAS ALONSO |
| Final | 8/7/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 8/7/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 8/7/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 8/22/2024 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 8/22/2024 | Approved | SABAS ALONSO |