4624 3/4 N EAGLE ROCK BLVD 90041
Certificate Information: 4624 3/4 N EAGLE ROCK BLVD 90041
- Application / Permit
- 21010-10000-06318
- Plan Check / Job No.
- B21LA22868
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW DETACHED ACCESSORY DWELLING UNIT AT REAR PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 7/2/2023
- Issuing Office
- Current Status
- CofO Issued on 12/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2021 | KEVIN MORALES |
| Corrections Issued | 12/20/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 8/10/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 8/25/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 9/8/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 9/22/2022 | KEVIN MORALES |
| Plan Check Approved | 3/3/2023 | KEVIN MORALES |
| Issued | 7/2/2023 | APPLICANT |
| CofO in Progress | 12/6/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 12/14/2024 | DEROLD HAUFF |
| CofO Issued | 12/14/2024 | DEROLD HAUFF |
| Permit Finaled | 12/14/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 6/14/2022 | STEVE MELGAR |
| Construction near power lines | Cleared | 7/6/2022 | TINA MIRANDA |
| Low Impact Development | Cleared | 7/8/2022 | ANTHONY VARGAS |
| GPI Written Notices | Cleared | 8/10/2022 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 8/10/2022 | KEVIN MORALES |
| Roof/Waste drainage to street | Cleared | 8/10/2022 | STEVE MELGAR |
| Miscellaneous | Cleared | 12/19/2022 | LOUIS ORTEGA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/26/2023 | Partial Inspection | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 11/29/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 12/6/2023 | Not Ready for Inspection | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 12/6/2023 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 12/6/2023 | Approved | ROY SPAULDING |
| Service/Power Release | 12/6/2023 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 2/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 2/20/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 2/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Wood Frame | 2/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 3/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 3/5/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Sewer | 3/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 3/5/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 3/5/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 3/13/2024 | Partial Approval | LILIANA PORTILLO |
| Insulation | 3/27/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 4/3/2024 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 4/3/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 4/10/2024 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 5/24/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 5/30/2024 | Approved | ALIZAH MAYAGOITIA |
| Pre-Inspection | 7/2/2024 | Partial Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 9/12/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/9/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 10/9/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 10/9/2024 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 10/9/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/17/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 10/17/2024 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 10/17/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 11/5/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 12/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/5/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Service/Power Release | 12/5/2024 | Approved | ALIZAH MAYAGOITIA |