208-210 E 61ST ST 90003
Certificate Information: 208-210 E 61ST ST 90003
- Application / Permit
- 21010-10000-06311
- Plan Check / Job No.
- B21LA22833
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED 1 CAR GARAGE AT FRONT AND 2 CAR GARAGE AT REAR.
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Current Status
- CofO Issued on 4/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | KHEDER ALRAZAA |
| Corrections Issued | 12/26/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 1/3/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/6/2022 | APPLICANT |
| Plan Check Approved | 11/10/2022 | KHEDER ALRAZAA |
| Issued | 11/10/2022 | APPLICANT |
| CofO in Progress | 4/12/2023 | BRENDAN MORELLI |
| CofO Issued | 4/15/2023 | DEROLD HAUFF |
| Permit Finaled | 4/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 3/5/2022 | CINDY JOSSELYN |
| Sewer availability | Cleared | 10/20/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 10/31/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 10/31/2022 | JEANIE LAM |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/16/2022 | Approved | BRENDAN MORELLI |
| Wood Frame | 12/16/2022 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Partial Approval | BRENDAN MORELLI |
| Insulation | 12/19/2022 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 1/24/2023 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Partial Approval | BRENDAN MORELLI |
| HVAC-Rough | 2/2/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 2/2/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 2/3/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/3/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 2/3/2023 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 2/3/2023 | Approved | BRENDAN MORELLI |
| Insulation | 2/6/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 2/23/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/23/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 3/31/2023 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Final | 4/11/2023 | Approved | BRENDAN MORELLI |
| Final | 4/11/2023 | Conditional Approval | BRENDAN MORELLI |
| Green Building Final | 4/11/2023 | Approved | BRENDAN MORELLI |
| HVAC-Final | 4/11/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 4/11/2023 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 4/11/2023 | SGSOV Approved | BRENDAN MORELLI |
| Service/Power Release | 4/11/2023 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 4/11/2023 | Approved | BRENDAN MORELLI |
| Final | 4/12/2023 | OK to Issue CofO | BRENDAN MORELLI |
| Service/Power Release | 4/12/2023 | Approved | BRENDAN MORELLI |