145-145 1/2 E 87TH PL 90003
Certificate Information: 145-145 1/2 E 87TH PL 90003
- Application / Permit
- 21010-10000-06308
- Plan Check / Job No.
- B21LA22823
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH GARAGE (FRONT)
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | STARR CHEN |
| Corrections Issued | 12/19/2021 | STARR CHEN |
| Quality Review Completed | 1/4/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 1/6/2022 | APPLICANT |
| Plan Check Approved | 4/21/2022 | STARR CHEN |
| Issued | 6/14/2022 | APPLICANT |
| CofO in Progress | 11/15/2022 | LILIANA PORTILLO |
| Permit Finaled | 12/1/2022 | DEROLD HAUFF |
| CofO Issued | 12/1/2022 | DEROLD HAUFF |
| Permit Finaled | 12/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 1/12/2022 | RICHARD REASER |
| Address approval | Cleared | 1/18/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | JEANIE LAM |
| Sewer availability | Cleared | 1/19/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 2/11/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/22/2022 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 3/28/2022 | LAURINDA MEADE |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 7/12/2022 | Partial Approval | LILIANA PORTILLO |
| Wood Frame | 7/12/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2022 | Partial Approval | LILIANA PORTILLO |
| Insulation | 7/14/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/17/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 8/18/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/22/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/22/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/26/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/26/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 8/26/2022 | Approved | LILIANA PORTILLO |
| Insulation | 8/26/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 8/26/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/6/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/6/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Drywall Nailing | 9/7/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/7/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/31/2022 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/10/2022 | Approved | LILIANA PORTILLO |
| Final | 11/10/2022 | Conditional Approval | LILIANA PORTILLO |
| Green Building Final | 11/10/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 11/10/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 11/10/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 11/10/2022 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 11/10/2022 | Approved | LILIANA PORTILLO |
| Final | 11/14/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 11/14/2022 | Approved | LILIANA PORTILLO |