5963-5965 N FAIR AVE 91601
Certificate Information: 5963-5965 N FAIR AVE 91601
- Application / Permit
- 21010-10000-06301
- Plan Check / Job No.
- B21LA22795
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX WITH GARAGE (REAR)
- Permit Issued
- Issued on 3/6/2024
- Issuing Office
- Metro
- Current Status
- Issued on 3/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | STARR CHEN |
| Corrections Issued | 12/19/2021 | STARR CHEN |
| Quality Review Completed | 1/4/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 1/12/2022 | APPLICANT |
| Plan Check Approved | 1/22/2024 | STARR CHEN |
| Issued | 3/6/2024 | APPLICANT |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 1/25/2022 | ANACANY HURTADO |
| Trees in Parkway | Cleared | 2/16/2022 | ADALBERTO VERA |
| Highway dedication | Cleared | 2/22/2022 | DAGOVERTO GUERRERO |
| Address approval | Cleared | 2/23/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/23/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 4/7/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 4/12/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 4/18/2022 | DAGOVERTO GUERRERO |
| Permit | Cleared | 1/11/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | E M C Development Solutions; Lic. No.: 1056785-B | 11052 HASTING COURT RANCHO CUCAMONGA, CA 91730 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 3/27/2024 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 5/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 5/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 9/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 9/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 10/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 10/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 10/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 10/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 10/28/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 11/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 1/27/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 1/27/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 1/30/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 1/30/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 2/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 2/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 3/23/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 3/23/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 3/23/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 3/23/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 3/23/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 3/23/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 4/3/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 4/3/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 4/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |